SCO
California Clean Energy Jobs Act Proposition 39 Program Audit
Read the report at California Clean Energy Jobs Act Proposition 39 Program ↗
PROGRAM AUDIT OF THE
CALIFORNIA CLEAN ENERGY
JOBS ACT
Audit Report
PROPOSITION 39 PROGRAM
Chapter 29, Statutes of 2013
July 1, 2019, through June 30, 2020
BETTY T. YEE
California State Controller
August 2021
BETTY T. YEE
California State Controller
August 9, 2021
Adrienne Alvord, Chair
Citizens Oversight Board
1516 9th Street, MS 19
Sacramento, CA 95814
Dear Ms. Alvord:
The State Controller’s Office audited a selection of completed projects related to the California
Clean Energy Jobs Act for the period of July 1, 2019, through June 30, 2020.
As of June 30, 2020, 313 local educational agencies (LEAs) reported $213,837,359 in completed
project costs and 31 community college districts (CCDs) reported $36,403,651 in completed
project costs. From the list of completed projects, we selected for audit 16 LEAs and four CCDs,
which together reported total expenditures of $39,178,611. Our audit found that:
Six LEAs and two CCDs sole-sourced a portion of their project costs, resulting in
unallowable costs of $1,411,867;
One LEA has unspent planning funds totaling $25,355, and two LEAs have unspent
implementation funds totaling $102,725;
One LEA and one CCD spent Proposition 39 funds on ineligible expenditures, resulting in
unallowable costs of $40,321;
Two LEAs earned interest, totaling $37,992, on their Proposition 39 funds but did not
spend it;
Eleven LEAs and three CCDs did not identify the projected energy savings in the awarded
contracts, and five LEAs and two CCDs did not have signed contracts with one or more of
their vendors;
Twelve LEAs submitted their final project completion reports after the deadline; and
One LEA is in violation of the energy measure payback period.
We also identified an issue that is not significant to the audit objective, but warrants the attention
of management. Specifically, we found that one LEA applied its unused planning funds to
program implementation. However, as these funds were not included in the LEA’s approved
energy expenditure plan, the amount of Proposition 39 funds paid to this LEA exceeded its
approved energy expenditure plan by $235,475.
Adrienne Alvord, Chair -2- August 9, 2021
This final audit report identifies six LEAs and two CCDs that sole-sourced a portion of their
project costs, in violation of Public Resources Code section 26235(c). This final audit report also
identifies one LEA and one CCD that spent Proposition 39 funds on ineligible expenditures.
Public Resources Code section 26240(h) states:
The Superintendent of Public Instruction shall require local educational agencies to pay back funds
if they are not used in accordance with state statute or regulations…The Chancellor of the
California Community Colleges shall require a community college to pay back funds if they are
not used in accordance with state statute or regulations…
Findings 1 and 3 are both apportionment-significant for LEAs. If you disagree with either
finding, you have 30 days from the date the State Controller’s Office emailed this report to
request a summary review of any apportionment-significant audit findings on the grounds of
substantial compliance. In addition, you have 60 days from delivery of this letter—or 30 days
following the conclusion of a summary review regarding the finding included in that review—to
file a formal appeal of any apportionment-significant audit findings on any one or more of the
grounds set forth in Education Code (EC) section 41344(d). The request for a summary review or
formal appeal should be submitted to the following address:
Executive Officer
Education Audit Appeals Panel
770 L Street, Suite 1100
Sacramento, California 95814
If you have any questions regarding the summary review process or the appeal process, please
see the Education Audit Appeals Panel (EAAP) website (www.eaap.ca.gov) or call EAAP at
(916) 445-7745.
LEAs working to resolve audit exceptions may request structured repayment plans under EC
section 41344. To request a repayment plan, the LEA must submit a letter to the California
Department of Education (CDE) within 90 days of receipt of this letter; within 30 days of
withdrawing or receiving a determination of a summary review if there is no appeal; or within
30 days of withdrawing or receiving a final determination regarding an appeal pursuant to EC
section 41344(a). More information on repayment plans can be found on the CDE’s website
(http://www.cde.ca.gov/fg/au/ag/resolution.asp) or by contacting the CDE, School Fiscal
Services Division, Categorical Allocations and Management Assistant Unit, at (916) 323-8068.
Findings 1 and 3 both have a fiscal impact on the affected CCDs. If you disagree with these two
findings, Title 5, section 59100, et seq. provides that the Chancellor for the California
Community Colleges has the authority to review audit findings involving CCDs. The request for
an appeal should be submitted to:
Amanda Voie, Specialist
Fiscal Accountability
College Finance and Facilities Planning Division
California Community Colleges Chancellor’s Office
1102 Q Street
Sacramento, CA 95811
Adrienne Alvord, Chair -3- August 9, 2021
You may also call the California Community Colleges Chancellor’s Office Fiscal Accountability
Office at (916) 323-1759 for more information.
If you have any questions about the audit findings, please contact Lisa Kurokawa, Chief,
Compliance Audits Bureau, by telephone at (916) 327-3138.
Sincerely,
Original signed by
KIMBERLY TARVIN, CPA
Chief, Division of Audits
KT/ls
cc: Jim Bartridge, Program and Policy Advisor
Citizens Oversight Board
Jack Bastida, Program Specialist
Citizens Oversight Board
Tony Thurmond, State Superintendent of Public Instruction
California Department of Education
Tami Pierson, Interim Director
Audits and Investigations Division
California Department of Education
Kelly Levario, Staff Services Manager II
Audits and Investigations Division
California Department of Education
Elizabeth Dearstyne, Director
School Fiscal Services Division
California Department of Education
Derrick Andrade, Education Fiscal Services Consultant
School Fiscal Services Division
California Department of Education
David Hochschild, Chair
California Energy Commission
Drew Bohan, Executive Director
California Energy Commission
Michael Sokol, Deputy Director
Efficiency Division
California Energy Commission
Armand Angulo, Assistant Deputy Director
Renewable Energy Division
California Energy Commission
Eloy Ortiz Oakley, Chancellor
California Community Colleges
Pamela Haynes, President
Board of Governors
California Community Colleges Chancellor’s Office
Adrienne Alvord, Chair -4- August 9, 2021
Lizette Navarette, Vice Chancellor
College Finance and Facilities Planning Division
California Community College Chancellor’s Office
Hoang Nguyen, Director of Facilities Planning
College Finance and Facilities Planning Division
California Community College Chancellor’s Office
Amanda Voie, Specialist
College Finance and Facilities Planning Division
California Community Colleges Chancellor’s Office
Mary C. Kelly, CPA, Executive Officer
Education Audit Appeals Panel
Jeffrey Hall, President
Board of Trustees
Allan Hancock Joint Community College District
Kevin G. Walthers, Ph.D., President
Allan Hancock Joint Community College District
Eric D. Smith, Associate Superintendent/Vice President
Finance and Administration
Allan Hancock Joint Community College District
Laura Becker, Director
Business Services
Allan Hancock Joint Community College District
Mark A. Lopez, President
Board of Education
Anaheim Elementary School District
Christopher Downing, Ed.D., Superintendent
Anaheim Elementary School District
Jesus Chavarria, Assistant Superintendent
Administrative Services
Anaheim Elementary School District
Priscilla Martinez, Director
Business Services
Anaheim Elementary School District
Isela Vazquez, Senior Director
Facilities, Planning and Construction
Anaheim Elementary School District
Jill McGrady, President
Board of Trustees
Antelope Valley Union High School District
David J. Vierra, Ph.D., Superintendent
Antelope Valley Union High School District
Brian Hawkins, Assistant Superintendent
Business Services
Antelope Valley Union High School District
Adrienne Alvord, Chair -5- August 9, 2021
Carleton Lincoln, Ed.D., Chief Executive Officer
Children of Promise Preparatory Academy
Samuel Shalhoub, President
Board of Trustees
Coast Unified School District
Scott Smith, Superintendent
Coast Unified School District
Annie Lachance, Chief Business Official
Coast Unified School District
Lillie Campbell, President
Board of Education
Community Collaborative Charter
Dr. Cindy Petersen, Superintendent
Community Collaborative Charter
Aaron Thornsberry, Chief Business Official
Community Collaborative Charter
Chrissa Gillies, President
Board of Trustees
Cotati−Rohnert Park Unified School District
Dr. Mayra Perez, Superintendent
Cotati–Rohnert Park Unified School District
Robert Marical, Chief Business Official
Cotati–Rohnert Park Unified School District
Josh Savage, Executive Director
Maintenance and Facilities
Cotati–Rohnert Park Unified School District
Linda Porras, President
Board of Education
Desert Sands Unified School District
Scott Bailey, Superintendent
Desert Sands Unified School District
Sonya Melendez, Director
Fiscal Services
Desert Sands Unified School District
Peter Landsberger, President
Board of Trustees
Foothill–De Anza Community College District
Judy C. Miner, Chancellor
Foothill–De Anza Community College District
Susan Cheu, Vice Chancellor
Business Services
Foothill–De Anza Community College District
Dr. Armine Hacopian, President
Board of Trustees
Glendale Community College District
Dr. David Viar, Superintendent/President
Glendale Community College District
Adrienne Alvord, Chair -6- August 9, 2021
Dr. Anthony Culpepper, Executive Vice President
Administrative Services
Glendale Community College District
Susan Courtey, Director
Business Services
Glendale Community College District
Ruben Mendoza, President
Board of Education
Madera Unified School District
Todd Lile, Superintendent
Madera Unified School District
Arelis Garcia, Chief Financial Officer
Fiscal Services
Madera Unified School District
Sandon Schwartz, Deputy Superintendent
Madera Unified School District
Rosalind Cox, Director
Facilities Planning and Construction Management
Madera Unified School District
Susan Harautuneian, Director
Purchasing Department
Madera Unified School District
Naomi Landry, President
Board of Education
Mattole Unified School District
Karen Ashmore, Superintendent
Mattole Unified School District
Shari Lovett, Director
Northern United–Humboldt Charter School
Charlene G. West, Ph.D., President
Board of Education
Modesto City Elementary School District
Sara Noguchi, Ed.D., Superintendent
Modesto City Elementary School District
Tim Zearley, Associate Superintendent
Business Services
Modesto City Elementary School District
Duane Wolterstorff, Senior Director
Business Services
Modesto City Elementary School District
Roger Orth, Senior Director
Maintenance and Operations
Modesto City Elementary School District
Tina Heimerdinger, President
Board of Education
Mountain Empire Unified School District
Patrick Keeley, Ed.D., Superintendent
Mountain Empire Unified School District
Adrienne Alvord, Chair -7- August 9, 2021
Gary Hobelman, Assistant Superintendent
Business Services
Mountain Empire Unified School District
Manuel Aguirre, President
Board of Trustees
Romoland School District
Trevor Painton, Superintendent
Romoland School District
Keith Bacon, Chief Business Official
Romoland School District
Mimi Capistrano, Fiscal Services Supervisor
Business Services
Romoland School District
Shanell Williams, President
Board of Trustees
San Francisco Community College District
Dianna Gonzales, J.D., Interim Chancellor
San Francisco Community College District
John al-Amin, Ph.D., Vice Chancellor
Finance and Administration
San Francisco Community College District
Marian Lam, Assistant Director Capital Planning
Office of Facilities and Capital Planning
San Francisco Community College District
Gabriela López, President
Board of Education
San Francisco Unified School District
Vincent Matthews, Ed.D., Superintendent
San Francisco Unified School District
Myong Leigh, Deputy Superintendent
Policy and Operations
San Francisco Unified School District
Meghan Wallace, Chief Financial Officer
Finance Department
San Francisco Unified School District
Paula Villescaz, President
Board of Education
San Juan Unified School District
Kent Kern, Superintendent
San Juan Unified School District
Kent Stephens, Deputy Superintendent
Business Support Services
San Juan Unified School District
Frank Camarda, Assistant Superintendent
Operations, Facilities and Transportation
San Juan Unified School District
Adrienne Alvord, Chair -8- August 9, 2021
Nicholas Arps, Director
Facilities, Construction and Modernization
San Juan Unified School District
Chris Ralston, Manager
Maintenance and Operations
San Juan Unified School District
Cherie Chenoweth, Business Operations Supervisor
Facilities, Maintenance & Transportation
San Juan Unified School District
Kimberly Braziel, President
Board of Trustees
Sunnyside Union School District
Steve Tsuboi, Superintendent-Principal
Sunnyside Union School District
Candy Alari, Business Manager
Sunnyside Union School District
Jaymes Lackey, President
Board of Trustees
Thermalito Union Elementary School District
Gregory Blake, Superintendent
Thermalito Union Elementary School District
Cody Walker, Assistant Superintendent
Thermalito Union Elementary School District
Rachel Young, Accounting Specialist
Thermalito Union Elementary School District
Lisa Anderson, Executive Director
Fiscal Services
Butte County Office of Education
Corey Weber, Director of Fiscal Services
Business Services
Humboldt County Office of Education
Patricia Smith, Chief Financial Officer
Business Services
Los Angeles County Office of Education
Julie DeWall, Chief
Business and Administrative Services
Madera County Superintendent of Schools
Dean West, CPA, Associate Superintendent
Business Services
Orange County Department of Education
Tina Daigneault, Chief Business Official
Administrative and Business Services
Riverside County Office of Education
Nick Schweizer, Assistant Superintendent
Business Services
Sacramento County Office of Education
Adrienne Alvord, Chair -9- August 9, 2021
Michael Simonson, Deputy Superintendent
Business Services
San Diego County Office of Education
Sheldon K. Smith, Ed.D., Assistant Superintendent
Business Services
San Luis Obispo County Office of Education
Mary Downey, Deputy Superintendent
Business Services
Sonoma County Office of Education
Donald Gatti, Deputy Superintendent
Business Services
Stanislaus County Office of Education
Fernie Marroquin, Ed.D., Assistant Superintendent
Business Services
Tulare County Office of Education
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Contents
Audit Report
Summary ............................................................................................................................ 1
Background ........................................................................................................................ 1
Audit Authority .................................................................................................................. 4
Objective, Scope, and Methodology ................................................................................. 4
Conclusion .......................................................................................................................... 6
Follow-up on Prior Audit Findings .................................................................................. 7
Views of Responsible Officials .......................................................................................... 8
Restricted Use .................................................................................................................... 8
Schedule 1—Total Completed Proposition 39 Program Costs for
Local Educational Agencies ....................................................................... 9
Schedule 2—Total Completed Proposition 39 Program Costs for
Community College Districts ..................................................................... 16
Findings and Recommendations ........................................................................................... 17
Observation and Recommendation ...................................................................................... 27
Appendix—Audit Results by Local Educational Agency and
Community College District ....................................................................... A1
Attachment A—Antelope Valley Union High School District’s Response to Audit Results
Attachment B—Children of Promise Preparatory Academy’s Response to Audit Results
Attachment C—Madera Unified School District’s Response to Audit Results
Attachment D—Romoland School District’s Response to Audit Results
Attachment E—Sunnyside Union School District’s Response to Audit Results
Attachment F—Foothill–De Anza Community College District’s Response to Audit Results
Attachment G—Glendale Community College District’s Response to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Audit Report
Summary The State Controller’s Office (SCO) audited a selection of completed
projects related to the California Clean Energy Jobs Act for the period of
July 1, 2019, through June 30, 2020.
As of June 30, 2020, 313 local educational agencies (LEAs) reported
$213,837,359 in completed project costs and 31 community college
districts (CCDs) reported $36,403,651 in completed project costs. From
the list of completed projects, we selected for audit 16 LEAs and four
CCDs, which together reported total expenditures of $39,178,611. Our
audit found that:
Six LEAs and two CCDs sole-sourced a portion of their project costs,
resulting in unallowable costs of $1,411,867;
One LEA has unspent planning funds totaling $25,355, and two LEAs
have unspent implementation funds totaling $102,725;
One LEA and one CCD spent Proposition 39 funds on ineligible
expenditures, resulting in unallowable costs of $40,321;
Two LEAs earned interest, totaling $37,992,on their Proposition 39
funds but did not spend it;
Eleven LEAs and three CCDs did not identify the projected energy
savings in the awarded contracts, and five LEAs and two CCDs did
not have signed contracts with one or more of their vendors;
Twelve LEAs submitted their final project completion reports after the
deadline; and
One LEA is in violation of the energy measure payback period.
We also identified an issue that is not significant to the audit objective, but
warrants the attention of management. Specifically, we found that one
LEA applied its unused planning funds to program implementation.
However, as these funds were not included in the LEA’s approved energy
expenditure plan (EEP), the amount of Proposition 39 funds paid to this
LEA exceeded its approved EEP by $235,475.
A separate summary of the audit results for the 16 LEAs and four CCDs
selected for audit is included as an Appendix to this report.
Background The California Clean Energy Jobs Act was created with the approval of
Proposition 39 (Chapter 29, Statutes of 2013) in the November 2012
statewide election. The statute changed the corporate income tax code to
allocate projected revenue from the General Fund to the Clean Energy Job
Creation Fund for five fiscal years, beginning with fiscal year
(FY) 2013-14. Under the initiative, it is estimated that up to $550 million
is available annually to be appropriated by the California State Legislature
for purposes of funding eligible projects that create jobs in California
while improving energy efficiency and expanding clean
energy generation.
-1-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Senate Bill 73 requires that 89% of the funds deposited annually into the
Clean Energy Job Creation Fund be made available to LEAs for energy
efficiency and clean energy projects, and 11% be made available to CCDs
for energy efficiency and clean energy projects.
An eligible energy project is an installation at or modification to a school
site that improves energy efficiency or expands clean energy generation.
Energy efficiency measures include heating, ventilation, and air
conditioning (HVAC) system retrofits and various interior and exterior
retrofits; clean energy generation measures include photovoltaic (solar)
panels. All facilities within an LEA are eligible for Proposition 39 program
funding.
Citizens Oversight Board
Proposition 39 also established the Citizens Oversight Board to review
expenditures, audit the Clean Energy Job Creation Fund, and maintain
transparency and accountability of the Fund. The California Treasurer,
Attorney General, and State Controller each appoint three members of the
Citizens Oversight Board; the California Energy Commission (CEC) and
the California Public Utilities Commission appoint two ex officio
members.
California Department of Education
The California Department of Education (CDE) is responsible for
distributing Proposition 39 funding to LEAs that serve grade K-12
students. CDE allocates funds based on the following formula:
85% based on average daily attendance reported as of the second
principal apportionment for the prior year; and
15% based on the number of students eligible for free and reduced-
priced meals in the prior year.
These funds may be used by LEAs for energy efficiency and clean energy
projects, as well as related energy planning, energy training, and energy
management. LEAs are required to submit an EEP to the CEC for
consideration and approval. An EEP includes a technical description and
project specifications for the proposed eligible energy measures. Funds are
released to an LEA only after the CEC approves the EEP.
LEAs with prior-year average daily attendance of 1,000 or lower are
eligible to receive funding for both the current year and the following year
in the current year. LEAs that select this option do not receive a funding
allocation in the following year.
LEAs whose first year of eligibility was FY 2013-14 also had the option
of requesting a portion of that year’s award allocation for energy planning
activities without submitting an EEP to the CEC. The energy planning
funds can be spent only on the following four activities:
Energy audits and energy surveys/assessments;
Proposition 39 program assistance;
Hiring or retaining an energy manager; and
Energy-related training.
-2-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Any unused energy planning funds must be applied toward implementing
energy projects from an LEA’s approved EEP.
California Energy Commission
The CEC is the primary state agency responsible for energy policy and
planning. Public Resources Code (PRC) section 26235(a) requires the
CEC to establish guidelines in consultation with the State Superintendent
of Public Instruction, the Chancellor of the California Community
Colleges, and the California Public Utilities Commission.
On December 19, 2013, the CEC adopted program implementation
guidelines, to which substantive revisions have been made. For this audit
period, we referred to Proposition 39: California Clean Energy Jobs Act –
2016 Program Implementation Guidelines (2016 Program
Implementation Guidelines). These guidelines provide direction to LEAs
on the types of awards and the required proposals, explain the screening
and evaluation criteria, describe the standards to be used to evaluate
project proposals, and outline the award process.
The 2016 Program Implementation Guidelines include a savings-to-
investment ratio (SIR) calculation. To be approved for Proposition 39
funding, energy projects must achieve an SIR above 1.0. For example, for
every dollar invested in the eligible energy project, the LEA must accrue
over $1 in savings. The SIR calculation is based on the present value of
the savings divided by project installation costs, subtracting rebates and
other grant funding sources. The 2016 Program Implementation
Guidelines also include a formula for estimating job creation benefits,
pursuant to PRC section 26235(e)(10).
The CEC also developed the Proposition 39: California Clean Energy
Jobs Act – 2015 Energy Expenditure Plan Handbook (EEP Handbook),
which includes step-by-step instructions to assist LEAs in completing the
required forms.
California Community Colleges Chancellor’s Office
The California Community Colleges Chancellor’s Office (CCCCO) is the
state agency that oversees the California community college system. The
CCCCO is responsible for distributing Proposition 39 funding to
individual CCDs. The funds may be used by CCDs for energy efficiency
and alternative energy projects, along with related improvements and
repairs, that contribute to reducing operating costs and improving health
and safety conditions in the community college system.
On May 29, 2013, the CCCCO issued the California Community Colleges
Energy Project Guidance to assist CCDs with implementing projects that
meet the Proposition 39 requirements. The CCCO subsequently published
an addendum to the California Community Colleges Energy Project
Guidance; the Proposition 39 Implementation Guidelines were issued in
October 2013 and revised in January 2014, April 2015, and April 2016.
For this audit period, we referred to the April 2015 version of the
Proposition 39 Implementation Guidelines. We also verified that the
Project Funding Application (Form B) and the CCC Proposition 39 Job
Creation Tracking Report (Form J) submitted by each CCD complied with
revisions contained in the April 2016 guidelines.
-3-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Projects must be consistent with the State’s energy loading order, which
guides the State’s energy policies and decisions according to the following
priority order: 1) decreasing electricity demand by increasing energy
efficiency and reducing energy usage in periods of high demand or cost,
2) meeting new energy supply needs with renewable resources, and
3) meeting new energy generation needs with clean fossil-fuel generation.
CCDs have been pursuing and implementing energy efficiency and
renewable energy projects for many years. The California Public Utilities
Commission administers the California Community Colleges/Investor
Owned Utilities Energy Efficiency Partnership, a joint program of the
CCDs and California’s four investor-owned utilities. This public-private
partnership has been advocating, promoting, and supporting energy
efficiency in the California Community College system since 2006. The
partnership has successfully reduced energy usage throughout the
community college system, resulting in savings of over $12 million.
Audit Authority Government Code section 12410 and PRC section 26210 provide the legal
authority to conduct this audit.
Government Code section 12410 states, in part, “The Controller shall
superintend the fiscal concerns of the state and audit the disbursement of
any state money for correctness, legality, and for sufficient provisions of
law for payment.”
The SCO’s interagency agreement with the Citizens Oversight Board,
pursuant to PRC section 26210(d)(2), commissions the SCO to review a
selection of completed projects to assess the effectiveness of the
expenditures in meeting the objectives of the California Clean Energy Jobs
Act.
Objective, Scope, On July 21, 2020, we entered into an agreement with the Citizens
Oversight Board to conduct an audit of a selection of completed projects
and Methodology
(80% LEA projects and 20% CCD projects) to evaluate their effectiveness
in meeting the objectives of the Clean Energy Job Creation Fund’s
program guidelines. We selected 16 LEAs and four CCDs for audit.
To achieve our audit objective for the LEA K-12 Proposition 39 Program,
we selected 16 of 313 LEAs with project costs totaling $30,994,040 and
determined whether:
Planning funds were expended in accordance with program
requirements and unspent planning funds were applied towards
implementing eligible energy projects approved by the CEC;
The LEA submitted an EEP to the CEC consistent with the LEA’s
priority of eligible projects;
The CEC approved the EEP in compliance with the 2016 Program
Implementation Guidelines and EEP Handbook;
The approved EEP included:
o A signed utility data release form from the LEA allowing the CEC
to access both historical and future utility billing data;
-4-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
o A benchmarking process established by the CEC to determine a
prioritized plan for implementing the eligible energy projects;
o An identification of eligible energy projects according to any one
of the three methods available to LEAs (these include an energy
survey; an American Society of Heating, Refrigerating and Air-
Conditioning Engineering Level 2 energy audit; or data analytics);
o A SIR that adheres to the cost-effectiveness determination set
forth by the CEC; and
o A job-creation benefits estimation that adheres to the formula set
forth by the CEC.
The final report to the CEC contained the information outlined in PRC
section 26240, subdivision (b), paragraphs (1) through (7);
The LEA did not use a sole-source process to award funds;
The LEA had a signed contract that identified project specifications,
costs, and projected energy savings;
The LEA supported project costs;
The LEA paid back Proposition 39 funds if the project was torn down,
remodeled, or deemed surplus and sold prior to the payback of the
project; and
If the LEA received funds for the Bus Replacement Program, the
replacement bus was present and in operation.
Our audit responsibilities included verifying the existence of school
buses purchased through the State’s Bus Replacement Program,
pursuant to PRC section 26205.5 (a) (1). The CDE provided
information to us verifying that the following LEAs received such
funds during the fiscal year ended June 30, 2020:
o Anaheim Elementary School District − $2,501,732;
o Madera Unified School District − $1,660,045; and
o Thermalito Union Elementary School District − $1,660,047.
California schools were closed for the 2020-21 school year while
following statewide COVID-19 protocols. As a result, we were unable
to verify the existence of the school buses purchased by these three
LEAs with funds allocated from the Bus Replacement Program.
Errors found in the selected samples were not projected to the intended
(total) population.
To achieve our audit objective for the CCD Proposition 39 Program, we
selected four of 31 CCDs with completed project costs totaling $8,184,571
and determined whether:
The CCD submitted a Proposition 39 Funding Application to the
CCCCO, and the CCCCO approved the application consistent with its
Proposition 39 Implementation Guidelines;
The CCD submitted a Call for Projects form that identified projects as
energy efficiency or renewable energy generation;
-5-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The Proposition 39 Close-out Project Completion form and the
Annual Project Expenditure Report submitted to the CCCCO
contained the following information:
o The estimated amount of energy saved, accompanied by specific
energy consumption and utility bill cost data for the individual
facility where the project is located;
o The nameplate rating of the new clean energy generation method
installed;
o The number of trainees resulting from the project;
o The amount of time between awarding financial assistance and
completing the project or training activities;
o The entity’s energy intensity before and after project completion,
as determined by an energy rating or benchmark system; and
o The number of direct full-time equivalent employees created by
each project and the average number of months or years of
utilization of each of these employees.
The CCD did not use a sole-source process to award funds;
The CCD had a signed contract that identified project specifications,
costs, and projected energy savings;
The CCD supported project costs; and
The CCD paid back the Proposition 39 Program funds if the project
was torn down, remodeled, or deemed surplus and sold prior to the
payback of the project.
Errors found in the selected samples were not projected to the intended
(total) population.
We did not audit the LEAs’ and CCDs’ financial statements.
We conducted this audit in accordance with generally accepted
government auditing standards. Those standards require that we plan and
perform the audit to obtain sufficient, appropriate evidence to provide a
reasonable basis for our findings and conclusions based on our audit
objective. We believe that the evidence obtained provides a reasonable
basis for our findings and conclusions based on our audit objective.
Conclusion As a result of conducting the audit procedures, we found instances of
noncompliance with the audit objective outlined in the Objective, Scope,
and Methodology section. These instances are quantified in the Schedules
and described in the Findings and Recommendations section of this report.
We selected 16 LEAs and four CCDs with completed projects for audit.
These 20 agencies reported total completed project costs of $39,178,611
($30,994,040 for LEAs and $8,184,571 for CCDs). Our audit found:
Six LEAs and two CCDs sole-sourced a portion of their project costs,
resulting in unallowable costs of $1,411,867;
-6-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
One LEA has unspent planning funds totaling $25,355, and two LEAs
have unspent implementation funds totaling $102,725;
One LEA and one CCD spent Proposition 39 funds on ineligible
expenditures, resulting in unallowable costs of $40,321;
Two LEAs earned interest, totaling $37,992, on their Proposition 39
funds but did not spend it;
Eleven LEAs and three CCDs did not identify the projected energy
savings in the awarded contracts, and five LEAs and two CCDs did
not have signed contracts with one or more of their vendors;
Twelve LEAs submitted their final project completion reports after the
deadline; and
One LEA is in violation of the energy measure payback period.
We also identified an issue that is not significant to the audit objective, but
warrants the attention of management. Specifically, we found that one
LEA applied its unused planning funds to program implementation.
However, as these funds were not included in the LEA’s approved EEP,
the amount of Proposition 39 funds paid to this LEA exceeded its approved
EEP by $235,475. This issue is described in the Observation and
Recommendation section of this report.
Follow-up on We previously conducted an audit of 17 LEAs and four CCDs. The audit
scope included projects completed between July 1, 2018, and June 30,
Prior Audit
2019. We issued our audit report on June 30, 2020. The report found that:
Findings
Six LEAs sole-sourced a portion of their project costs, resulting in
unallowable costs of $9,537,047;
Twelve LEAs and four CCDs did not identify the projected energy
savings in the awarded contracts, and four LEAs did not have a signed
contract;
One LEA spent Proposition 39 funds on ineligible expenditures,
resulting in unallowable costs of $3,034;
Nine LEAs submitted their final project completion reports after the
deadline; and
Two LEAs applied their unspent planning funds to program
implementation. However, as these funds were not included in the
LEAs’ approved EEPs, the amount of Proposition 39 funds paid to
these LEAs exceeded their approved EEPs by $232,713.
The 16 LEAs and four CCDs selected for the current audit were not
previously audited under the Proposition 39 Program. However, we found
that the current audit identifies the same issues noted in prior audit reports.
-7-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Views of We discussed our audit results with representatives of the 16 LEAs and
four CCDs selected for testing during audit fieldwork, and via email at the
Responsible
end of the audit. All responses to the findings have been included in the
Officials
LEA’s or CCD’s respective section of the Appendix; and each formal
response received on letterhead has been included as an Attachment to this
report.
Restricted Use This report is solely for the information and use of the Citizens Oversight
Board, the CDE, the CEC, the CCCCO, Allan Hancock Joint Community
College District, Anaheim Elementary School District, Antelope Valley
Union High School District, Children of Promise Preparatory Academy,
Coast Unified School District, Community Collaborative Charter School,
Cotati–Rohnert Park Unified School District, Desert Sands Unified School
District, Foothill–De Anza Community College District, Glendale
Community College District, Madera Unified School District, Mattole
Valley Charter School, Modesto City Elementary School District,
Mountain Empire Unified School District, Romoland School District, San
Francisco Community College District, San Francisco Unified School
District, San Juan Unified School District, Sunnyside Union School
District, Thermalito Union Elementary School District, and the SCO; it is
not intended to be and should not be used by anyone other than these
specified parties. This restriction is not intended to limit distribution of this
report, which is a matter of public record, and is available on the SCO
website at https://www.sco.ca.gov.
Original signed by
KIMBERLY TARVIN, CPA
Chief, Division of Audits
August 9, 2021
-8-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1—
Total Completed Proposition 39 Program Costs
for Local Educational Agencies
July 1, 2019, through June 30, 2020
Program Planning Amount
Local Educational Agency Implementation Funds 1 Total Unallowable Reference 2, 3
Completed projects selected for audit:
Anaheim Elementary $ 1,824,952 $ 293,311 $ 2,118,263 $ (76,871) Finding 1, 5, 6
Antelope Valley Union High School District 3 3 ,832,092 82,595 3 ,914,687 (16,298) Finding 1, 4, 5
Children of Promise Preparatory Academy 267,668 - 267,668 (25,846) Finding 1, 5, 7
Coast Unified 224,784 57,272 282,056 - Finding 5, 6
Community Collaborative Charter 197,200 114,500 311,700 - Finding 5, 6
Cotati–Rohnert Park Unified School District (EEP #4951, #5126) 1 ,190,735 130,000 1 ,320,735 - Finding 5, 6
Desert Sands Unified School District 6 ,521,118 - 6 ,521,118 - Finding 6
Madera Unified 4 ,790,235 292,039 5 ,082,274 (339,941) Finding 1, 5, 6
Mattole Valley Charter (#159) 168,197 26,362 194,559 (82,933) Finding 2, 6
Modesto City Elementary3 3 ,707,593 230,589 3 ,938,182 - Finding 4, 6
Mountain Empire Unified 459,915 114,629 574,544 (574,544) Finding 1, 5, 6
Romoland Elementary 839,484 42,400 881,884 - Finding 3, 6
San Francisco Unified 1 ,177,670 720,401 1 ,898,071 (32,074) Finding 1, 5
San Juan Unified School District (EEP #1895, #1897) 2 ,480,055 400,049 2 ,880,104 - Finding 5, 6
Sunnyside Union Elementary 218,192 - 218,192 (45,147) Finding 2, 5
Thermalito Union 590,003 - 590,003 - Finding 5, 6
Total, completed projects selected for audit $ 28,489,893 $ 2,504,147 $ 30,994,040 4 $ (1,193,654)
Completed projects not selected for audit:
ABC Unified School District $ 515,315 $ 245,671 $ 760,986
Academia Avance Charter 254,194 24,200 278,394
Academy for Academic Excellence 419,354 15,000 434,354
Alliance Collins Family College–Ready High 267,378 22,912 290,290
Alliance Dr. Olga Mohan High 72,543 24,125 96,668
Alliance Marc & Eva Stern Math and Science 238,840 23,216 262,056
Alta-Dutch Flat Union Elementary 22,352 15,745 38,097
Amador County Office of Education 209,824 53,121 262,945
Amador County Unified School District 753,213 130,000 883,213
American River Charter 202,519 50,760 253,279
Antelope Elementary 53,511 45,801 99,312
Apple Valley Unified 3,171,159 - 3 ,171,159
Aspire Lionel Wilson Academy 277,974 3 ,000 280,974
Bay Area Technology 238,707 26,334 265,041
Beardsley Elementary 538,068 69,640 607,708
Beverly Hills Unified 727,510 130,000 857,510
Big Lagoon Union Elementary 61,732 15,808 77,540
Borrego Springs Unified 272,956 5 ,600 278,556
Briggs Elementary 249,681 - 249,681
Browns Elementary 244,892 8 ,900 253,792
Buellton Union Elementary 236,273 30,000 266,273
Burbank Unified 1,176,556 86,000 1 ,262,556
Burlingame Elementary 598,361 79,624 677,985
Butte County Office of Education 206,080 51,568 257,648
Butte Valley Unified 210,167 53,406 263,573
Butteville Union Elementary 182,129 51,702 233,831
Calexico Unified 2,349,489 - 2 ,349,489
Caliber: Beta Academy 137,799 - 137,799
California Military Institute 361,874 - 361,874
California Virtual Academy @ Los Angeles 302,991 40,751 343,742
-9-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1 (continued)
Program Planning
Local Educational Agency Implementation Funds 1 Total
Completed projects not selected for audit (continued):
Campbell Union High 282,626 83,000 365,626
Camptonville Academy 261,617 3,900 265,517
Camptonville Elementary 69,400 7 ,500 76,900
Cardiff Elementary 226,272 30,900 257,172
Castro Valley Unified (EEP #481) 1 ,873,513 70,230 1 ,943,743
Castro Valley Unified (EEP #1008) 43,653 70,230 113,883
Cayucos Elementary 241,501 13,808 255,309
Central Elementary 1 ,109,381 - 1,109,381
Central Union Elementary School District 109,559 - 109,559
Centralia Elementary 1 ,080,655 - 1,080,655
Chaffey Joint Union High School District 1,155,044 177,543 1 ,332,587
Charter Oak Unified 1 ,201,778 27,393 1 ,229,171
Chawanakee Unified 281,778 - 281,778
Chula Vista Elementary School District 1 ,279,516 - 1,279,516
Chula Vista Elementary School District –
Chula Vista Learning Community Charter 153,599 - 153,599
Classical Academy 466,339 51,815 518,154
Cloverdale Unified 559,030 - 559,030
Clovis Unified 5 ,960,995 20,300 5 ,981,295
Coastal Academy 419,590 46,769 466,359
Colusa Unified 560,368 - 560,368
Community Outreach Academy 383,256 118,500 501,756
Community School for Creative Education 232,342 25,523 257,865
Competitive Edge Charter Academy 210,874 52,978 263,852
Connecting Waters Charter 37,537 - 37,537
Coronado Unified 636,727 - 636,727
Corona–Norco Unified 1 ,702,434 - 1,702,434
Cottonwood Creek Charter 203,810 50,874 254,684
Cox Academy 198,098 58,967 257,065
Creative Connections Arts Academy 264,314 15,133 279,447
Culver City Unified 1 ,510,184 130,000 1 ,640,184
Davis Joint Unified 664,543 127,429 791,972
Di Giorgio Elementary 152,100 32,033 184,133
Dinuba Unified 1 ,649,005 - 1,649,005
Douglas City Elementary 205,295 36,814 242,109
Downtown Value 271,098 - 271,098
Dunsmuir Joint Union High School District 15,000 - 15,000
e3 Civic High 214,766 - 214,766
Edison Elementary 527,054 44,514 571,568
El Dorado Union High School District –
Virtual Academy at Shenandoah 75,370 - 75,370
Excellence in Justice and Education –
Elementary Academy Charter 159,871 24,228 184,099
Excellence in Justice and Education –
Middle Academy 148,984 21,551 170,535
El Dorado Union High 1 ,393,215 - 1,393,215
El Rancho Unified 2,182,312 107,790 2 ,290,102
El Tejon Unified 229,949 50,505 280,454
Elk Hills Elementary 139,934 45,000 184,934
Environmental Charter Middle 251,369 22,500 273,869
Etiwanda Elementary 1 ,390,710 86,801 1 ,477,511
Eureka Union 654,661 - 654,661
Fairfax Elementary 560,089 96,347 656,436
Feaster (Mae L.) Charter 167,051 - 167,051
Fillmore Unified 870,808 76,618 947,426
Franklin Elementary 247,930 11,407 259,337
-10-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1 (continued)
Program Planning
Local Educational Agency Implementation Funds 1 Total
Completed projects not selected for audit (continued):
Fuente Nueva Charter 65,804 15,437 81,241
Fullerton Elementary 2 ,967,739 186,943 3 ,154,682
Fusion Charter 154,692 - 154,692
Futures High 264,505 8,642 273,147
Glenn County Office of Education 134,302 13,630 147,932
Golden Feather Union Elementary 168,850 17,363 186,213
Grenada Elementary School 250,000 - 250,000
Harvest Ridge Coop Charter 72,500 50,030 122,530
Hemet Unified 4 ,961,020 308,652 5 ,269,672
Heritage K-8 241,660 25,050 266,710
Heritage Peak Charter 300,925 108,979 409,904
High Tech Elementary North County 173,616 - 173,616
High Tech High North County 250,372 10,000 260,372
High Tech Middle North County 249,716 10,000 259,716
Higher Learning Academy 212,161 52,804 264,965
Highland Academy 202,235 - 202,235
Highlands Community Charter 171,157 - 171,157
Hilmar Unified 408,824 - 408,824
Holtville Unified 575,865 - 575,865
Hughson Unified 239,449 - 239,449
Ida Jew Academies 267,016 - 267,016
Inspire Charter School 30,138 - 30,138
Inspire Charter School - South 30,964 - 30,964
Ivy Academia 225,803 103,902 329,705
Janesville Union Elementary 243,425 15,974 259,399
Jefferson Elementary 33,804 - 33,804
Jefferson Union High 1 ,024,930 - 1,024,930
John B. Riebli Elementary 255,633 - 255,633
Journey 209,649 15,000 224,649
Julian Charter (EEP #2442) 48,336 76,516 124,852
Julian Charter (EEP #2464) 23,220 76,516 99,736
Julian Charter (EEP #5276) 305,280 103,069 408,349
Julian Union High 227,079 - 227,079
Jurupa Unified School District 2 ,866,610 - 2,866,610
Kashia Elementary 19,155 - 19,155
Kenwood 200,250 - 200,250
Keppel Union Elementary 680,616 - 680,616
Kerman Unified (EEP #5691) 1 ,114,936 100,220 1 ,215,156
Kerman Unified (EEP #5693) 82,953 100,220 183,173
Kernville Union Elementary 275,004 17,766 292,770
Kings County Office of Education 247,465 17,422 264,887
Kingsburg Joint Union High 426,665 105,002 531,667
La Habra City School District 400,060 1,469 401,529
La Mesa–Spring Valley (EEP #1634) 2 ,502,000 - 2,502,000
La Mesa–Spring Valley (EEP #2227) 663,148 - 663,148
Lakeside Union Elementary 26,675 54,610 81,285
Lamont Elementary 766,365 14,449 780,814
Las Virgenes Unified 748,330 30,515 778,845
Lassen Union High 213,316 53,046 266,362
Laytonville Unified 270,142 - 270,142
Lazear Charter Academy 172,688 54,435 227,123
Lemoore Middle College High 254,724 - 254,724
Lemoore Union Elementary 724,322 - 724,322
Leroy Greene Academy 213,136 51,913 265,049
Liberty Elementary 242,897 22,404 265,301
-11-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1 (continued)
Program Planning
Local Educational Agency Implementation Funds 1 Total
Completed projects not selected for audit (continued):
Liberty Union High 1,676,113 29,640 1 ,705,753
Lincoln Street 43,142 - 43,142
Lindsay Unified 582,408 47,315 629,723
Literacy First Charter 265,823 2 ,000 267,823
Live Oak Elementary 576,660 - 576,660
Livermore Valley Joint Unified School District 1 ,067,942 159,280 1 ,227,222
Loma Vista Immersion Academy 206,794 - 206,794
Long Valley Charter 182,793 - 182,793
Los Alamitos Unified 649,435 101,500 750,935
Los Banos Unified 2 ,403,936 143,945 2 ,547,881
Los Feliz Charter School for the Arts 236,934 26,327 263,261
Los Olivos Elementary 200,702 50,206 250,908
Lost Hills Union Elementary 285,625 - 285,625
Lucerne Valley Unified 292,354 - 292,354
Madera County Office of Education 136,717 22,469 159,186
Maricopa Unified 265,435 5 ,000 270,435
Mark West Charter 82,761 5 ,000 87,761
Mark West Union Elementary 238,895 25,642 264,537
McCloud Union Elementary 69,500 9 ,000 78,500
Mendocino County Office of Education 123,009 30,000 153,009
Merced City Elementary 2 ,554,393 144,172 2 ,698,565
Mesa Union Elementary 241,496 15,000 256,496
Mill Valley Elementary 444,140 - 444,140
Minarets Charter High 254,974 - 254,974
Miwok Valley Language Academy Charter 205,650 55,355 261,005
Modesto City High 3 ,478,316 - 3,478,316
Modoc Joint Unified School District 106,651 - 106,651
Monte Rio Union Elementary 79,097 - 79,097
Moreno Valley Unified School District 3 ,168,481 154,000 3 ,322,481
Morongo Unified 1 ,153,768 - 1,153,768
Mount Pleasant Elementary 600,247 - 600,247
Napa County Office of Education 257,130 - 257,130
Napa Valley Language Academy 184,675 26,065 210,740
Nevada County Office of Education 252,803 - 252,803
New Designs Charter 272,111 29,764 301,875
New Hope Elementary 210,147 53,000 263,147
Newcastle Charter 252,930 - 252,930
Newcastle Elementary School District 252,546 - 252,546
NextGeneration STEAM Academy 87,764 16,036 103,800
Novato Charter School 110,415 - 110,415
Oakland Charter Academy 229,724 26,242 255,966
Oakland Military Institute, College Preparatory Academy 219,125 20,975 240,100
Oakley Union Elementary School District 1 ,136,222 - 1,136,222
Orange County School of Arts 516,492 - 516,492
Ojai Unified 592,810 - 592,810
Old Adobe Elementary Charter 256,375 - 256,375
Old Adobe Union 197,750 53,802 251,552
Old Town Academy K-8 Charter 201,299 50,491 251,790
Orchard View 145,060 50,158 195,218
Orland Joint Unified 550,494 - 550,494
Oroville Union High 483,023 64,485 547,508
Oxford Preparatory Academy–South Orange County 230,653 25,654 256,307
Pacific View Charter 268,984 - 268,984
Pajaro Valley Unified 1 ,874,426 - 1,874,426
Palmdale Elementary School District 267,905 215,000 482,905
-12-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1 (continued)
Program Planning
Local Educational Agency Implementation Funds 1 Total
Completed projects not selected for audit (continued):
Panama–Buena Vista Union 604,080 124,191 728,271
Pathways Charter 173,976 43,650 217,626
Patterson Joint Unified 1 ,336,732 75,000 1 ,411,732
Peninsula Union 61,816 15,459 77,275
Petaluma Accelerated Charter 30,439 - 30,439
Pioneer Union Elementary 79,827 - 79,827
Pixley Union Elementary 548,978 28,341 577,319
Placer County Office of Education 232,359 24,052 256,411
Pleasant Valley Joint Union Elementary 162,275 26,054 188,329
Princeton Joint Unified 258,758 - 258,758
PUC Santa Rosa Charter Academy 32,965 26,450 59,415
Raisin City Elementary 248,869 24,645 273,514
Ramona City Unified 1 ,260,328 17,651 1 ,277,979
Redwood Academy of Ukiah 115,080 51,100 166,180
Richfield Elementary School District (EEP #85) 101,046 50,523 151,569
Richfield Elementary School District (EEP #5367) 105,758 50,523 156,281
River Delta Joint Unified 533,710 34,904 568,614
River Montessori Elementary Charter 219,906 32,354 252,260
River Oak Charter 111,787 51,883 163,670
Riverbank Language Academy 205,502 55,513 261,015
Riverbank Unified 538,386 42,315 580,701
Riverdale Joint Unified 556,855 41,790 598,645
Riverside Unified School District 1 ,458,325 - 1,458,325
Robla Elementary 568,675 - 568,675
Rocketship Discovery Prep 47,832 22,989 70,821
Rocketship Los Suenos Academy 107,117 3,000 110,117
Rocketship Mateo Sheedy Elementary 108,056 3,000 111,056
Rocketship Mosaic Elementary 47,070 22,988 70,058
Rocketship Si Se Puede Academy 86,113 3 ,000 89,113
Rocky Point Charter 245,504 - 245,504
Rowland Unified 3 ,566,146 523 3,566,669
Saddleback Valley Unified School District 938,474 354,087 1 ,292,561
Saint Helena Unified 425,000 70,548 495,548
San Bruno Park Elementary 542,327 68,134 610,461
San Dieguito Union High 1 ,238,876 145,004 1 ,383,880
San Jacinto Unified School District 1 ,176,797 136,615 1 ,313,412
San Lorenzo Unified (EEP #690) 2 ,278,595 135,000 2 ,413,595
San Lorenzo Unified (EEP #2620) 324,530 135,000 459,530
San Lucas Union Elementary 78,960 404 79,364
San Luis Coastal Unified School District 394,252 130,000 524,252
San Luis Obispo County Office of Education (EEP #1679) 231,062 21,047 252,109
San Luis Obispo County Office of Education (EEP #2588) 7 ,894 21,048 28,942
San Miguel Elementary 232,735 25,642 258,377
Sanger Academy Charter 281,532 - 281,532
Sanger Unified School District 2 ,329,544 138,419 2 ,467,963
Santa Clara Elementary 65,448 10,000 75,448
Santa Cruz City Elementary 600,396 - 600,396
Sausalito Marin City School District 225,608 33,402 259,010
SAVA: Sacramento Academic and Vocational Academy 201,882 59,500 261,382
Scotts Valley Unified 154,916 - 154,916
Sherman Thomas Charter High 64,503 12,000 76,503
Sherman Thomas Charter School 135,808 22,000 157,808
Sherwood Montessori 206,788 - 206,788
Shiloh Charter 67,917 10,063 77,980
Shiloh Elementary 24,636 3 ,600 28,236
-13-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1 (continued)
Program Planning
Local Educational Agency Implementation Funds 1 Total
Completed projects not selected for audit (continued):
Sierra Charter 218,724 53,420 272,144
Sierra Sands Unified 1 ,117,243 29,900 1 ,147,143
Silver Oak High Public Montessori Charter 73,105 3 ,750 76,855
Simi Valley Unified 1 ,746,135 20,000 1 ,766,135
Smythe Academy of Arts and Sciences 456,715 113,755 570,470
Snowline Joint Unified School District 1 ,442,806 130,000 1 ,572,806
Solana Beach Elementary 598,908 35,500 634,408
Somis Union 262,170 - 262,170
Sonoma Mountain Elementary 255,892 - 255,892
Soquel Union Elementary 393,251 - 393,251
South Fork Union 247,544 15,662 263,206
Southern Trinity Joint Unified School District 73,100 - 73,100
Spencer Valley Elementary 67,482 5 ,875 73,357
Sunridge Charter School 150,060 50,269 200,329
Sutter County Office of Education 256,947 13,822 270,769
Taylion High Desert Academy/Adelanto 100,071 - 100,071
Taylion San Diego Academy 59,578 - 59,578
Tehama County Office of Education 137,991 9,500 147,491
Temecula Preparatory 298,228 - 298,228
Temecula Valley Charter School 118,606 - 118,606
Temecula Valley Unified School District (EEP #669) 4 ,030,524 - 4,030,524
Temecula Valley Unified School District (EEP #2256) 1,439,247 - 1,439,247
Tierra Pacifica Charter 144,056 - 144,056
Tracy Joint Unified (EEP #5647) 2 ,571,013 - 2,571,013
Tracy Joint Unified (EEP #5648) 899,155 - 899,155
Travis Unified 1 ,190,057 6 ,500 1 ,196,557
Trona Joint Unified 264,408 - 264,408
Tustin Unified School District 107,737 - 107,737
Twain Harte 254,236 7 ,853 262,089
Twin Hills Charter Middle School 152,430 50,935 203,365
Twin Hills Union Elementary 154,120 51,648 205,768
Twin Ridges Elementary 25,906 4 ,720 30,626
Twin Rivers Charter 266,677 - 266,677
Two Rock Union 206,869 47,500 254,369
Ukiah Unified School District (EEP #2417) 1 ,133,153 43,359 1 ,176,512
Ukiah Unified School District (EEP #2421) 241,018 43,359 284,377
University Preparatory Academy Charter 254,012 - 254,012
Urban Corps of San Diego County Charter 250,000 - 250,000
Urban Discovery Academy Charter 256,376 - 256,376
Urban Montessori Charter 181,486 25,709 207,195
Vacaville Unified 83,563 85,898 169,461
Ventura Unified 1 ,601,709 166,865 1 ,768,574
Victor Elementary 2 ,879,234 127,145 3 ,006,379
Vineland Elementary 304,508 - 304,508
Visalia Unified (EEP #2301) 100,000 - 100,000
Visalia Unified (EEP #5032) 367,650 379,039 746,689
Wasco Union High 570,476 28,125 598,601
Washington Middle College High 218,918 - 218,918
Weaver Union 438,448 95,351 533,799
West Covina Unified School District 251,283 136,277 387,560
Western Center Academy 122,184 6 ,500 128,684
Western Placer Unified 1 ,427,559 47,976 1 ,475,535
Westminster 2 ,381,332 - 2,381,332
Westside Preparatory Charter 215,497 54,128 269,625
Willits Elementary Charter 218,732 2 ,500 221,232
-14-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 1 (continued)
Program Planning
Local Educational Agency Implementation Funds 1 Total
Completed projects not selected for audit (continued):
Woodlake Unified 285,677 21,000 306,677
Woodward Leadership Academy 82,772 - 82,772
Yreka Union Elementary 297,727 1,272 298,999
Yuba County Career Preparatory Charter 247,059 17,632 264,691
Yuba County Office of Education 209,221 52,852 262,073
Total, completed projects not selected for audit 171,797,027 11,046,292 182,843,319
Total completed projects $ 200,286,920 $ 13,550,439 $ 213,837,359
_________________________
1 The planning funds are requested directly from CDE before an EEP is submitted.
2 See the Findings and Recommendations section.
3 The following districts earned interest on Proposition 39 allocations but did not spend it: Antelope Valley Union
High School District ($15,829) and Modesto City Elementary School District ($22,163). The unspent earned interest
is not included in the Amount Unallowable column, as it was not part of the overall EEP total. See Finding 4 –
Unspent earned interest.
4 We tested 100% of the costs reported, totaling 30,994,040, for the 16 LEAs selected for audit.
-15-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Schedule 2—
Total Completed Proposition 39 Program Costs
for Community College Districts
July 1, 2018, through June 30, 2019
Program Amount
Community College District Implementation Unallowable Reference 1
Completed projects selected for audit:
Allan Hancock Joint Community College District $ 1,061,036 $ ( 126,552) Finding 1, 3, 5
Foothill–De Anza Community College District 2 ,726,499 (219,741) Finding 1, 5
Glendale Community College District 1 ,913,134 - Finding 5
San Francisco Community College District 2 ,483,902 - Finding 5
Total, completed projects selected for audit $ 8,184,571 2 $ ( 346,293)
Completed projects not selected for audit:
Antelope Valley Community College District $ 929,063
Compton Community College District 397,311
Copper Mountain Community College District 97,928
El Camino Community College District 437,754
Feather River Community College District 26,763
Gavilan Joint Community College District 148,082
Imperial Community College District 252,607
Lassen Community College District 271,822
Long Beach Community College District 2 ,167,096
Los Angeles Community College District 12,367,389
Los Rios Community College District 1 ,478,202
Merced Community College District 576,807
Mt. San Jacinto Community College District 691,421
Napa Valley Community College District 441,699
North Orange County Community College District 323,791
Pasadena Area Community College District 1 ,202,000
Rancho Santiago Community College District 370,781
Redwoods Community College District 254,213
Rio Hondo Community College District 1 ,172,061
Riverside Community College District 1 ,362,786
San Bernardino Community College District 471,464
San Joaquin Delta Community College District 882,818
Santa Clarita Community College District 501,448
Santa Monica Community College District 276,830
Solano Community College District 552,010
Sonoma County Junior College District 357,497
West Kern Community College District 207,437
Total, completed projects not selected for audit $ 28,219,080
Total completed projects $ 36,403,651
______________________
1 See the Findings and Recommendations section.
2 We tested 100% of the costs reported, totaling $8,184,571, for the four CCDs selected for audit.
-16-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Findings and Recommendations
FINDING 1— We found that six LEAs and two CCDs sole-sourced a portion of their
project costs, totaling $1,411,867, as follows:
Sole-sourced project
costs
Local Educational Agency/ Contract
Community College District Amount
Anaheim Elementary School District $ 76,871
Antelope Valley Union High School District 1 6,298
Children of Promise Preparatory Academy 2 5,846
Madera Unified School District 339,941
Mountain Empire Unified School District 574,544
San Francisco Unified School District 3 2,074
Subtotal, Local Educational Agencies 1,065,574
Allan Hancock Joint Community College District1 126,552
Foothill–De Anza Community College District 219,741
Subtotal, Community College Districts 346,293
Total $ 1 ,411,867
1 We found that of the $126,552 that Allan Hancock Joint Community
College District expended on sole-sourced contracts; $34,513 was
also applied to ineligible expenditures (see Finding 3).
These six LEAs and two CCDs did not provide supporting documentation
to show that they considered other vendors before awarding contracts.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h) states:
The Superintendent of Public Instruction shall require local educational
agencies to pay back funds if they are not used in accordance with state
statute or regulations…The Chancellor of the California Community
Colleges shall require a community college to pay back funds if they are
not used in accordance with state statute or regulations…
PUC section 388(b) states:
The Department of General Services or any other state or local agency
intending to enter into an energy savings contract or a contract for an
energy retrofit project may establish a pool of qualified energy service
companies based on qualifications, experience, pricing, or other
pertinent factors. Energy service contracts for individual projects
undertaken by any state or local agency may be awarded through a
competitive selection process to individuals or firms identified in the
pool. The pool of qualified energy service companies and contractors
shall be reestablished at least every two years or shall expire.
-17-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, in part:
Districts shall not use a sole-source process to award grant proceeds.
Districts may use the best-value criteria as defined in paragraph (1) of
subdivision (c) of Section 20133 of the Public Contract Code to award
funds. Best value is defined as “a value determined by objective criteria
related to price, features, functions, and life-cycle costs.”
Exhibit N (Contracting “Best Practices” Fact Sheet) of the CCCCO’s
Proposition 39 Implementation Guidelines states, in part:
To fully comply with that “Best Value” criteria and the prohibition
against sole source contracting when utilizing [its] Prop 39 funds, a
District will need to engage in a two-step process that accomplishes the
following:
1. Request for Qualification (RFQ): Pre-qualifies energy project
contractors based on several criteria including energy project
history, team member qualifications, firm financial viability, and
experience working with Community Colleges, AND
2. Request for Proposals (RFP): Identifies and evaluates the specific
project workscope, schedule, and other requirements where multiple
contractors (at least two, three would be better) submit proposals for
District evaluation and consideration. Typically, the RFP should
include the following elements and respondent submittal
requirements:
Proposed workscope
Request price and life-cycle economics
Technical proposal and identification of specific equipment to
be installed
Energy savings
Project approach
Schedule
Exceptions
Exhibit N continues:
A comprehensive RFQ/RFP evaluation process should always be used
when implementing Proposition 39 funded projects. This process can
either be combined into a single solicitation, or can use a two-step,
separate RFQ & RFP process.
We have interpreted the PRC section 26235(c) prohibition against “[using]
a sole source process to award funds” as a requirement to use a competitive
bidding process. Competitive processes improve cost-effectiveness,
prevent favoritism, and make the procurement process transparent.
These LEAs and CCDs contracted with various vendors for their
Proposition 39 Program energy upgrade projects. Despite the
implementation guidance and best practices, the LEAs and CCDs used
noncompetitive processes to sign contracts with these vendors and, thus,
did not ensure the cost effectiveness of these services.
-18-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that:
The CDE take appropriate action to recover Proposition 39 funds from
LEAs that sole-sourced their project costs in violation of PRC section
26235(c); and
The CCCCO take appropriate action to recover Proposition 39 funds
from CCDs that sole-sourced their project costs in violation of PRC
section 26235(c).
No additional recommendation for LEAs and CCDs is applicable to this
finding, as the Proposition 39 Program has ended.
LEAs’ and CCDs’ Responses
We notified the six LEAs and two CCDs of this finding during audit
fieldwork and at the end of the audit via email. Findings and
Recommendations for individual LEAs and CCDs are included in the
Appendix. All responses to the findings have been included in the LEA’s
and CCD’s respective section of the Appendix; and each formal response
received on letterhead has been included as an Attachment to this report.
FINDING 2— We found that one LEA has unspent planning funds of $25,355, and two
LEAs have unspent program implementation funds totaling $102,725.
Unspent funds
These LEAs spent less on their projects than they had budgeted. The
following table summarizes this finding:
Unspent planning funds:
Mattole Valley Charter School $ 25,355
Subtotal, unspent planning funds 25,355
Unspent program implementation funds:
Mattole Valley Charter School 57,578
Sunnyside Union Elementary School District 45,147
Subtotal, unspent program implementation funds 102,725
Total unspent funds $ 128,080
The CEC’s 2016 Program Implementation Guidelines state on page 5:
The SSPI [State Superintendent of Public Instruction] is responsible for
administering awards to LEAs that serve grade K-12 students. These
funds may be used by LEAs for energy efficiency and clean energy
projects, related energy planning, energy training, energy management,
and energy projects with related non-energy benefits. LEAs are required
to submit an energy expenditure plan to the Energy Commission for
consideration and approval. Funds are released to the LEA only after the
Commission approves an LEA’s energy expenditure plan(s).
-19-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…the entity
shall submit a report of its project expenditures to the Citizens Oversight
Board....
PRC section 26240(h)(1) states:
The Superintendent of Public Instruction shall require local educational
agencies to pay back funds if they are not used in accordance with state
statute or regulations…
Recommendation
We recommend that the districts return the unspent funds to the State.
Although the Proposition 39 program has ended, the unspent funds must
be returned.
LEAs’ Responses
We notified the LEAs of this finding during audit fieldwork and at the end
of the audit via email. Findings and Recommendations for individual
LEAs are included in the Appendix. All responses to the findings have
been included in the LEA’s respective section of the Appendix; and each
formal response received on letterhead has been included as an
Attachment to this report.
CDE’s Response
We notified CDE of the unspent funds for the LEAs. CDE advised that it
will issue invoices to these districts in order to recover the unspent funds
and return them to the Job Creation Fund.
FINDING 3— We found that one LEA and one CCD applied Proposition 39 funds to
Ineligible project costs not approved by the CCCCO, resulting in ineligible
expenditures of $40,321.
expenditures
Local Educational Agency/
Community College District Amount
Romoland Elementary School District $ 5 ,808
Subtotal, Local Educational Agencies 5,808
Allan Hancock Joint Community College District 3 4,513
Subtotal, Community College Districts 3 4,513
Total $ 40,321
-20-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PRC section 26235(f) states:
The Superintendent of Public Instruction shall not distribute funds to an
LEA unless the LEA has submitted to the Energy Commission, and the
Energy Commission has approved, an expenditure plan that outlines the
energy projects to be funded. An LEA shall utilize a simple form
expenditure plan developed by the Energy Commission. The Energy
Commission shall promptly review the plan.…A portion of the funds
may be distributed to an LEA upon request for energy audits and other
plan development activities prior to submission of the plan.
The CEC’s 2016 Program Implementation Guidelines (“Energy Planning
Funds Reservation Option,” page 10) state:
LEAs whose first year of eligibility was fiscal year 2013-14, the first
year of the program, had the option of requesting a portion of that year’s
award allocation for energy planning activities in 2013-14 without
submitting an energy expenditure plan(s) to the Energy Commission.
This option was available only for the fiscal year 2013-14 award
allocation and was intended to be used for planning activities for
subsequent fiscal years (2013-14 through 2017-18)….
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 10.
Energy Project Implementation,” page 22) states:
Districts will be responsible for the implementation of projects funded
by Proposition 39. If, after approval and during implementation of a
project, the scope changes such that the energy savings, construction
costs, or cost-effectiveness are significantly affected, the Chancellor’s
Office will require that Districts provide a revised Project Application
(Form B) documenting the change of scope….
Step 10 of the CCCCO’s Proposition 39 Implementation Guidelines also
includes “adding a project not included in the approved Funding
Application” in the list of significant changes.
Recommendation
We recommend that:
The CDE take appropriate action to recover Proposition 39 funds from
LEAs whose project costs are not in compliance with the 2016
Program Implementation Guidelines; and
The CCCCO take appropriate action to recover Proposition 39 funds
from CCDs whose project costs are not in compliance with the
Proposition 39 Implementation Guidelines.
LEA’s and CCD’s Responses
We notified the LEA and the CCD of this finding during audit fieldwork
and at the end of the audit via email. Findings and Recommendations for
individual LEAs and CCDs are included in the Appendix. All responses
to the findings have been included in the LEA’s respective section of the
Appendix; and each formal response received on letterhead has been
included as an Attachment to this report.
-21-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
FINDING 4— We found that two LEAs earned interest, totaling $37,992, on their
Unspent earned Proposition 39 allocations but did not spend it. These LEAs completed all
of their energy projects, and applied all of their awarded Proposition 39
interest
funds to all projects within their approved EEPs. As the Proposition 39
program has ended and there are no remaining eligible energy projects on
which the LEAs can expend the earned interest, it should be returned to
the Clean Energy Job Creation Fund, as shown in the table below:
Unspent earned interest:
Antelope Valley Union High School District $ 1 5,829
Modesto City Elementary School District 22,163
Total unspent earned interest $ 3 7,992
The CEC’s 2016 Program Implementation Guidelines (“Interest Earned
on Proposition 39 Funds,” page 10) state:
Any interest earned on Proposition 39 funds shall be expended only
toward Proposition 39 eligible energy projects. LEAs should make every
effort to track interest earned from Proposition 39 allocations separately
for use on Proposition 39 eligible energy projects and to facilitate
auditing in accordance with PRC 26206(e) and 26240(h)(1).
PRC section 26206(e) states, “All projects shall be subject to audit.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”
Recommendation
We recommend that the districts return the unspent earned interest to the
State. Although the Proposition 39 program has ended, the unspent funds
must be returned.
LEAs’ Responses
We notified the two LEAs of this finding during audit fieldwork and at the
end of the audit via email. Findings and Recommendations for individual
LEAs are included in the Appendix. All responses to the findings have
been included in the LEA’s respective section of the Appendix; and each
formal response received on letterhead has been included as an
Attachment to this report.
CDE’s Response
We notified CDE of the unspent interest earned by the two LEAs. Prior to
issuance of this report, CDE emailed instructions to the LEAs on how they
can return the unspent earned interest to CDE. CDE will follow up with
the LEAs to assist with this recovery.
-22-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
FINDING 5— We found that 11 LEAs and three CCDs did not identify projected energy
No projected energy savings in the awarded contracts as required. In addition, five LEAs and
two CCDs did not have signed contracts. The table below summarizes this
savings identified
finding:
and/or no signed
contract Projected
Energy
Savings Not No Signed
Identified Contract
Local Educational Agency
Anaheim Elementary School District1 X X
Antelope Valley Union High School District2 X X
Children of Promise Preparatory Academy3 X
Coast Unified School District4 X
Community Collaborative Charter X
Cotati–Rohnert Park Unified School District X
Madera Unified School District X
Mountain Empire Unified School District X X
San Francisco Unified School District5 X
San Juan Unified School District (EEP #1895 and EEP #1897) X X
Sunnyside Union Elementary School District6 X
Thermalito Union Elementary School District X
Community College District
Allan Hancock Joint Community College District X
Foothill–De Anza Community College District7 X X
Glendale Community College District8 X
San Francisco Community College District X
1 We found that Anaheim Elementary School District did not have signed contracts for six vendors. In addition, we found that two of the awarded
contracts did not identify the projected energy savings as required.
2 We found that Antelope Valley Union High School District did not have signed contracts for two vendors.
3 We found that two of Children of Promise Preparatory Academy's awarded contracts did not identify the projected energy savings as required.
4 We found that two of Coast Unified School District's awarded contracts did not identify the projected energy savings as required.
5 We found that two of San Francisco Unified School District's awarded contracts did not identify the projected energy savings as required.
6 We found that two of Sunnyside Union Elementary School District's awarded contracts did not identify the projected energy savings as required.
7 We found that four of Foothill–De Anza Community College District's awarded contracts did not identify the projected energy savings as required.
8 We found that three of Glendale Community College District's awarded contracts did not identify the projected energy savings as required.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, “Projects funded by awards shall
require contracts that identify the project specifications, costs, and
projected energy savings.”
This finding does not result in questioned costs; however, ensuring that
contracts are signed and include projected energy savings helps to ensure
that program objectives are achieved.
-23-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
No recommendation for LEAs and CCDs is applicable to this finding, as
the Proposition 39 program has ended and the finding does not identify
any questioned costs.
LEAs’ and CCDs’ Responses
We notified the affected LEAs and CCDs of this finding during audit
fieldwork and at the end of the audit via email. Findings and
Recommendations for individual LEAs and CCDs are included in the
Appendix. All responses to the finding have been included in the LEA or
CCD’s respective section of the Appendix; and each formal response
received on letterhead has been included as an Attachment to this report.
FINDING 6— We found that 12 LEAs submitted their final project completion reports
Final project after the deadline. Each LEA is required to submit a final project
completion report to the CEC 12 to 15 months after its EEP is completed.
completion report
An EEP is considered complete when the LEA has completed all measures
submitted late
in the approved EEP.
The following table identifies the number of months the final report was
submitted after the project was completed:
Local Educational Agency Months
Anaheim Elementary School District 37
Coast Unified School District 31
Community Collaborative Charter School 23
Cotati–Rohnert Park Unified School District:
EEP #4951 61
EEP #5126 16
Desert Sands Unified School District 52
Madera Unified School District 22
Mattole Valley Charter School 21
Modesto City Elementary School District 16
Mountain Empire Unified School District 23
Romoland Elementary School District 17
San Juan Unified School District (EEP #1895) 23
Thermalito Union Elementary School District 19
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board…To the extent
practical, this report shall also contain information on any of the
following:
(1) The total final gross project cost before deducting any incentives or
other grants and the percentage of total project cost derived from the
Job Creation Fund...
-24-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
(2) The estimated amount of energy saved, accompanied by specified
energy consumption and utility bill cost data for the individual
facility where the project is located, in a format to be specified by
the Energy Commission.
(3) The nameplate rating of new clean energy generation installed.
(4) The number of trainees.
(5) The number of direct full-time equivalent employees and the
average number of months or years of utilization of each of these
employees.
(6) The amount of time between awarding of the financial assistance
and the completion of the project or training activities.
(7) The entity’s energy intensity before and after project completion, as
determined from an energy rating or benchmark system…
LEAs should submit timely final reports to the CEC to allow the CEC to
respond promptly to changing situations and maintain effective program
oversight. Information contained in the final reports is compiled into a
report that the CEC submits annually to the Citizens Oversight Board.
Recommendation
No recommendation for LEAs is applicable to this finding, as the
Proposition 39 program has ended and the finding does not identify any
questioned costs.
LEAs’ Responses
We notified the 12 LEAs of this finding during audit fieldwork and at the
end of the audit via email. Findings and Recommendations for individual
LEAs are included in the Appendix. All responses to the finding have been
included in the LEA’s respective section of the Appendix; and each formal
response received on letterhead has been included as an Attachment to
this report.
FINDING 7— We found that one LEA is in violation of the energy measure payback
Violation of energy period.
measure payback
Children of Promise Preparatory Academy closed on June 30, 2020, after
period
Inglewood Unified School District denied the school’s charter petition. As
a result, the school ceased operations. A court-appointed receiver has been
designated to oversee disposal of the charter school’s assets.
The facility is currently vacant and for sale as a charter school site;
however, until this facility is sold to an entity that will continue using the
facility as a school site, the LEA is in violation of the energy measure
payback period.
Per the CEC’s 2016 Program Implementation Guidelines (“Step 8: Energy
Project Tracking and Reporting,” page 33), “LEAs must not sell or
demolish the approved energy measure installed with Proposition 39
program award funding prior to the payback of the energy measure.”
-25-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that the CEC monitor the sale of Children of Promise
Preparatory Academy facilities to ensure that they continue being used as
school sites.
LEA’s Response
We notified the LEA of this finding during audit fieldwork and at the end
of the audit via email. The Finding and Recommendation for this LEA, in
addition to a summary of the LEA’s response, is included in the Appendix.
The school’s formal response, received on letterhead, has been included
as an Attachment to this report.
-26-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Observation and Recommendation
We found that one LEA applied its unused planning funds to program
OBSERVATION—
implementation. However, as these funds were not included in the LEA’s
Unused planning
approved EEP, the amount of Proposition 39 funds paid to the LEA
funds
exceeded its approved EEP by $235,475, as follows:
A B C = B−A
Program Planning Total Total Unused
Local Educational Agency Implementation Funds EEP Approved CDE Apportionment Planning Funds
Antelope Valley Union High School District $ 5,017,378 $ 107,595 $ 5 ,124,973 $ 5,360,448 $ 2 35,475
We reviewed Antelope Valley Union High School District’s accounting
ledgers and found that the district received funds in excess of the total
amounts indicated in the EEPs approved by the CEC.
LEAs had the option of requesting planning funds for energy planning
activities in FY 2013-14 without submitting an EEP to CEC. The funds
were intended to be used for planning activities for FY 2013-14 through
FY 2017-18. Any unused planning funds can be applied toward
implementing energy projects that are part of an approved EEP.
The district opted to use only a portion of its planning funds, and did not
apply the remaining funds toward program implementation. Therefore, the
district has unused planning funds of $235,475.
PRC section 26235(f) states:
The Superintendent of Public Instruction shall not distribute funds to an
LEA unless the LEA has submitted to the Energy Commission, and the
Energy Commission has approved, an expenditure plan that outlines the
energy projects to be funded. An LEA shall utilize a simple form
expenditure plan developed by the Energy Commission. The Energy
Commission shall promptly review the plan.…A portion of the funds
may be distributed to an LEA upon request for energy audits and other
plan development activities prior to submission of the plan.
The CEC’s 2016 Program Implementation Guidelines (“Energy Planning
Funds Reservation Option,” page 10) state:
LEAs whose first year of eligibility was fiscal year 2013-14, the first
year of the program, had the option of requesting a portion of that year’s
award allocation for energy planning activities in 2013-14 without
submitting an energy expenditure plan(s) to the Energy Commission.
This option was available only for the fiscal year 2013-14 award
allocation and was intended to be used for planning activities for
subsequent fiscal years (2013-14 through 2017-18)….
The CEC’s 2016 Program Implementation Guidelines (“Unused Energy
Planning Awards,” page 13) also state that “Any unused energy planning
funds shall be applied toward implementing eligible energy project(s)
approved as part of an LEA’s energy expenditure plan(s).”
-27-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
We recommend that:
CDE take appropriate action in response to the LEA’s unused planning
funds; and
CDE and CEC account for unused planning funds that were applied to
program implementation without being included in an approved EEP.
CDE’s Response
We notified CDE of the Observation via email on June 14, 2021. The CDE
responded by email on June 14, 2021, stating that it will contact the LEA
about the unused planning funds.
-28-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Appendix—
Audit Results by Local Educational Agency
and Community College District
Local Educational Agencies
Anaheim Elementary School District .............................................................................................. A2
Antelope Valley Union High School District .................................................................................. A5
Children of Promise Preparatory Academy ..................................................................................... A14
Coast Unified School District .......................................................................................................... A17
Community Collaborative Charter School ....................................................................................... A19
Cotati–Rohnert Park Unified School District .................................................................................. A21
Desert Sands Unified School District .............................................................................................. A23
Madera Unified School District ....................................................................................................... A25
Mattole Valley Charter School ........................................................................................................ A30
Modesto City Elementary School District ....................................................................................... A32
Mountain Empire Unified School District ....................................................................................... A35
Romoland School District ................................................................................................................ A37
San Francisco Unified School District ............................................................................................. A40
San Juan Unified School District ..................................................................................................... A42
Sunnyside Union School District ..................................................................................................... A44
Thermalito Union Elementary School District ................................................................................ A46
Community College Districts
Allan Hancock Joint Community College District .......................................................................... A48
Foothill–De Anza Community College District .............................................................................. A52
Glendale Community College District ............................................................................................. A57
San Francisco Community College District .................................................................................... A60
-A1-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Anaheim Elementary School District
Proposition 39 Program
Background The California Energy Commission (CEC) approved Anaheim
Elementary School District’s energy expenditure plan (EEP) for
$1,824,952, consisting of $373,000 for energy management services and
$1,451,952 for program implementation. The district used its program
implementation funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures* Savings
District Office $ 51,236 Interior/exterior lighting retrofit $ 16,644
Guinn (James M.) Elementary 15,509 Interior lighting retrofit 7,690
Henry (Patrick) Elementary 6 ,949 HVAC−Packaged/split system AC/Heat Pump/VRF 433
Jefferson (Thomas) Elementary 7 ,604 HVAC−Packaged/split system AC/Heat Pump/VRF 1,168
Juarez (Benito) Elementary 113,100 Building envelope−insulation; interior lighting retrofit 7,338
Keys preschool and training facility 13,328 Interior lighting retrofit 7,415
Marshall (John) Elementary 9 ,000 HVAC Controls−Energy management system -
Olive Street Elementary 32,205 HVAC−Packaged/split system AC/Heat Pump/VRF 2,116
Orange Grove Elementary 2 ,896 HVAC−Packages/split system AC/Heat Pump/VRF 621
Revere (Paul) Elementary 4 ,480 Building envelope−insulation 4,125
Ross (Betsy) Elementary 4 ,021 HVAC-Packaged/split system AC/Heat Pump/VRF 643
Interior lighting retrofit; building envelope−windows/
Stoddard (Alexander J.) Elementary 1 ,167,910 1 4,947
skylights; HVAC−Packaged/split system AC/Heat Pump/VRF
Sunkist Elementary 23,714 HVAC−Packaged/split system AC/Heat Pump/VRF 3,155
Total $ 1,451,952 $ 66,295
*HVAC: heating, ventilation, and air conditioning; AC: air conditioning; VRF: variable refrigerant flow
With these energy efficiency measures, the district reported a combined
savings-to-investment ratio (SIR) of 1.01 and the creation of 8.13 direct
job-years.
In addition, the district received $293,311 in planning funds directly from
the California Department of Education (CDE), which it used for
screening and audits.
Audit Results
We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Sole-sourced project costs
We found that the district sole-sourced its contracts with Global Lighting
Organization ($28,837), Geary Pacific Supply ($6,949), US Air
Conditioning Distributors ($24,044), Johnson Controls ($9,000), and
Johnstone Supply ($8,041). The district did not provide supporting
documentation to show that it considered other vendors before awarding
contracts to these five vendors. Therefore, we found that the district sole-
sourced these Proposition 39 contracts, totaling $76,871.
-A2-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Public Resources Code (PRC) section 26235(c) states, in part, “A
community college district or LEA [local educational agency] shall not
use a sole source process to award funds pursuant to this chapter.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”
Public Utilities Code (PUC) section 388(b) states:
The Department of General Services or any other state or local agency
intending to enter into an energy savings contract or a contract for an
energy retrofit project may establish a pool of qualified energy service
companies based on qualifications, experience, pricing, or other
pertinent factors. Energy service contracts for individual projects
undertaken by any state or local agency may be awarded through a
competitive selection process to individuals or firms identified in the
pool. The pool of qualified energy service companies and contractors
shall be reestablished at least every two years or shall expire.
No projected energy savings identified and/or no signed contracts
We reviewed the district’s contracts with DJM Construction Company and
Erickson-Hall Construction Co., and determined that the contracts do not
identify the projected energy savings. In addition, the district did not
support that it had signed contracts with Global Lighting Organization,
Geary Pacific Supply, Howard Industries, US Air Conditioning
Distributors, Johnson Controls, and Johnstone Supply.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion report submitted late
The district’s final report was submitted on September 12, 2019,
37 months after the reported project completion date of August 31, 2016.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
We recommend that the CDE take appropriate action to recover
Proposition 39 funds that the district expended on sole-sourced project
costs, in violation of PRC section 26235(c).
No additional recommendation is applicable, as the Proposition 39
program has ended.
-A3-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
District’s Response
We informed the district of the audit findings via email on June 1, 2021.
Priscilla Martinez, Director of Business Services, responded vie email on
June 10, 2021.
The district’s response to Finding 1 – Sole-sourced project costs, and
Finding 5 – No projected energy savings identified and/or no signed
contract, is as follows:
The District purchased equipment and supplies from the aforementioned
vendors [Global Lighting Co., Geary Pacific Supply, Howard Industries,
US Air Conditioning Distributors, and Johnstone Supply] in accordance
with Public Contract Code (PCC) section 20111(a) and section 22002(c).
PCC 20111(a) allowed the District to issue a purchase order with an
informal quote given that the amount purchased fell below the bid limit
threshold. Secondly, PCC 22002(c) established that the equipment and
supplies did not constitute a “public project” as defined by said code.
With this in mind, the District purchased equipment and supplies via a
legal binding instrument; a purchase order.
However, the District recognizes that the Prop. 39 CA Clean Energy Jobs
Act grant stipulated that districts obtain more than one quote for the
purchase of equipment and supplies. Moving forward, the District will
be consistent in applying this as best practice.
The district did not respond to Finding 6 – Final project completion report
submitted late.
SCO Comment
Our findings and recommendation remain unchanged.
-A4-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Antelope Valley Union High School District
Proposition 39 Program
Background The CEC approved Antelope Valley Union High School District’s EEP
for $3,832,092. The district used its program implementation funds for the
following energy efficiency measures:
Proposition 39 Reported
Share Used at Energy Annual Cost
School Site School Site Efficiency Measures* Savings
Antelope Valley High $ 279,179 Interior/exterior lighting retrofit $ 20,238
Eastside High 595,019 Interior/exterior lighting retrofit 43,417
Lancaster High 374,475 Interior/exterior lighting retrofit 32,210
Interior/exterior lighting retrofit; HVAC–Packaged/split system
Littlerock High 2,191,912 AC/Heat Pump/VRF 67,524
Quartz Hill High 391,507 Interior/exterior lighting retrofit 28,561
Total $ 3,832,092 $ 191,950
*HVAC: Heating, ventilation, and air conditioning; AC: air conditioning; VRF: variable refrigerant flow
With these energy efficiency measures, the district reported a combined
SIR of 1.06 and the creation of 21.46 direct job-years.
In addition, the district received $82,595 in planning funds directly from
the CDE, which it used for screening and audits.
We audited Proposition 39 program costs to ensure compliance with the
Audit Results
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and the EEP Handbook. We
identified the following audit issues.
Sole-sourced project costs
The district contracted with Lozano Smith, LLP for legal services
($6,398), and Brian Hayes for inspection services ($9,900). The district
did not provide supporting documentation to show that it considered other
vendors or agencies before awarding contracts to Lozano Smith, LLP and
Brian Hayes. Therefore, we found that the district sole-sourced these
Proposition 39 contracts, totaling $16,298.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”
PUC section 388(b) states:
The Department of General Services or any other state or local agency
intending to enter into an energy savings contract or a contract for an
energy retrofit project may establish a pool of qualified energy service
companies based on qualifications, experience, pricing, or other
-A5-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
pertinent factors. Energy service contracts for individual projects
undertaken by any state or local agency may be awarded through a
competitive selection process to individuals or firms identified in the
pool. The pool of qualified energy service companies and contractors
shall be reestablished at least every two years or shall expire.
Unspent earned interest
The district accumulated interest, totaling $15,829, on its allocations from
the Proposition 39 Program. The district’s approved EEP was completed
and the final report was submitted. The district applied all of its awarded
Proposition 39 funds to all projects within its approved EEP. As the
Proposition 39 program has ended and there are no remaining eligible
energy projects on which the district can expend the earned interest, it
should be returned to the Clean Energy Job Creation Fund.
We notified CDE of the unspent earned interest. Prior to issuance of this
report, CDE emailed instructions to the district on how it can return the
unused interest earned on Proposition 39 funds to CDE. CDE will follow
up with the district to assist with this recovery.
The CEC’s 2016 Program Implementation Guidelines (“Interest Earned
on Proposition 39 Funds,” page 10) state:
Any interest earned on Proposition 39 funds shall be expended only
toward Proposition 39 eligible energy projects. LEAs should make every
effort to track interest earned from Proposition 39 allocations separately
for use on Proposition 39 eligible energy projects and to facilitate
auditing in accordance with PRC 26206(e) and 26240(h)(1).
PRC section 26206(e) states, “All projects shall be subject to audit.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”
No projected energy savings identified and/or no signed contract
We reviewed the district’s contract with Trane, and determined that the
contract does not identify the projected energy savings. In addition, the
district did not provide support that it had a signed contract with Lozano
Smith, LLP.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
We also made the following observation:
Unused planning funds
We found that the district applied unused planning funds to program
implementation. However, these funds were not included in the district’s
approved EEP. As a result, the district received funding that exceeded its
approved EEP by$235,475.
-A6-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
We notified CDE of the Observation via email on June 14, 2021. The CDE
responded by email on June 14, 2021, stating that it will contact the LEA
about the unused planning funds.
PRC section 26235(f) states:
The Superintendent of Public Instruction shall not distribute funds to an
LEA unless the LEA has submitted to the Energy Commission, and the
Energy Commission has approved, an expenditure plan that outlines the
energy projects to be funded. An LEA shall utilize a simple form
expenditure plan developed by the Energy Commission. The Energy
Commission shall promptly review the plan.…A portion of the funds
may be distributed to an LEA upon request for energy audits and other
plan development activities prior to submission of the plan.
The CEC’s 2016 Program Implementation Guidelines (“Energy Planning
Funds Reservation Option,” page 10) state:
LEAs whose first year of eligibility was fiscal year 2013-14, the first
year of the program, had the option of requesting a portion of that year’s
award allocation for energy planning activities in 2013-14 without
submitting an energy expenditure plan(s) to the Energy Commission.
This option was available only for the fiscal year 2013-14 award
allocation and was intended to be used for planning activities for
subsequent fiscal years (2013-14 through 2017-18)….
The CEC’s 2016 Program Implementation Guidelines (“Unused Energy
Planning Awards,” page 13) also state that “Any unused energy planning
funds shall be applied toward implementing eligible energy project(s)
approved as part of an LEA’s energy expenditure plan(s).”
Recommendation
We recommend that the CDE take appropriate action to recover
Proposition 39 funds that the district expended on sole-sourced project
costs, in violation of PRC section 26235(c).
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit findings and Observation via email
on June 3, 2021. Brian Hawkins, Assistant Superintendent of Business
Services, responded by email dated June 22, 2021. The district’s response
letter is included as Attachment A.
The district’s response to Finding 1 – Sole-sourced project costs, is as
follows:
The District believes that it acted in good faith and complied with the
relevant program requirements in entering into these contracts.
A. It was not Clear that Proposition 39’s Limitation on Sole
Sourcing Applied to these Contracts.
Public Resources Code section 26235(c) (“Section 26235(c)”)
provides that an “LEA shall not use a sole source process to award
funds pursuant to this chapter. [An] LEA may use the best value
-A7-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
criteria as defined in paragraph (1) of subdivision (c) of
Section 20133 of the Public Contract Code to award funds pursuant
to this chapter.” Notably, Section 26235(c) does not define the term
“sole source” or describe the precise scope of the sole source
limitation.
Section 26235(c) provides that an “LEA may use the best value
criteria as defined in paragraph (1) of subdivision (c) of
Section 20133 of the Public Contract Code to award funds pursuant
to this chapter.” Public Contract Code section 20133, which has
since been repealed and replaced with Public Contract Code
section 22161, defines the term “best value” in the context of
design-build projects. (See Pub. Contract Code, § 22161, subd. (a).)
In the absence of other clear statutory language or guidance, it was
not clear that the sole source limitation also applied to the retention
of project consultants, such as legal counsel or the project inspector.
B. The District complied with the Sole Source Limitation even if it
applied to these Contracts.
Section 26235(c) limits sole sourcing but otherwise provides little
detail regarding the procurement methods that an LEA may use in
the Proposition 39 context. Importantly, however, the California
Energy Commission (“CEC”), in its “Frequently Asked Questions
California Clean Energy Jobs Act (Proposition 39),” (“FAQ”) sheds
some light on this issue, indicating that an “LEA shall defer to [its]
own procurement regulations and procedures, as long as they
reflect applicable state and local laws and regulations, and do
not conflict with the minimum legal standards specified
above.”…
Here, the District used its own procurement regulations and
applicable law. Public Contract Code section 20111 and
corresponding California Department of Education guidance
indicate that a school district, as of 2016, did not need to
competitively bid contracts for services that were valued at less than
$87,800. (Pub. Contract Code, § 20111, subd. (a)(1).) Government
Code section 50360 also permits a school district to “contract with
and employ any persons for the furnishing [of] special services and
advice in financial, economic, accounting, engineering, legal, or
administrative matters,” without bid or with a very informal process.
The contracts at issue are for legal and inspection services and thus
fall within the purview of Government Code section 53060. (See
also Education Code sections 35041.5 and 35204.) Additionally, the
contracts are valued at $945; $6,398; and $9,900, respectively, and
thus fall well-below the competitive bidding threshold. As a result,
according to general procurement law and District policy, the
District was permitted to contract with “any person[]” for these
services and was not required to undergo a competitive process.
The Guidelines permit LEAs to follow their own procurement
regulations and applicable law, so long as they do not conflict with
the Proposition 39 standards. In this case, the District informally
retained the firms and inspector in good faith and in compliance with
longstanding law, based on the belief it did not conflict with the sole
source limitation, as that limitation did not clearly apply to contracts
for these services.
-A8-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
C. The District Did Not Sole Source these Contracts.
Finally, the District did not “sole source” these contracts. While
Section 26235(c) does not define “sole source” as used in that
section, Public Resources Code section 25620.5(e) presents
analogous language, indicating that “single source” procurement
involves choosing from “two or more parties.” This statute further
explains that “sole source” procurement involves less competition
than single source, seemingly implying that sole source procurement
involves no form of choice between one option or another. (Pub.
Resources Code, § 25620.5, subd. [e].) So it is reasonable to view
“sole source” for the purposes of Proposition 39 to mean direct
contracting with one vendor without even considering other
vendors.
By using two different legal firms, by definition, the District did not
Sole Source its legal representation.
Thus, the District substantially and in good faith complied with the
sole source limitation.
The district’s response to Finding 4 – Unspent earned interest, and to the
Observation is as follows:
The District agrees with the SCO as to the amount of unused funds in the
amount of $46,373.00 and with the amount of interest earned for the
duration of the project of $15,829.00.
The district’s response to Finding 5 − No projected energy savings
identified and/or no signed contract, is as follows:
The District believes that it acted in good faith and complied with the
relevant program requirements in entering into these contracts.
A. Section 26206(d) Does not Apply to the District’s Contracts with
Atkinson and Lozano Smith.
Section 26206(d) provides, “All projects shall require contracts that
identify the project specifications, costs, and projected energy
savings.” Section 26206(d) is limited to contracts for “projects,” as
that term is used in the context of Proposition 39. The relevant
statutes do not define this term, but the Guidelines indicate that an
“eligible energy project” is “[a]n energy efficiency measure or
bundled group of energy efficiency measures and/or clean energy
installations (in or at one or more school sites) within an LEA.”
(Guidelines, H-3.) Accordingly, Section 26206(d) must be read to
mean that a contract for the implementation of energy efficiency
measures must include a description of projected energy savings.
Other related contracts—such as those for legal services—need not
include this information.
Therefore, the District’s contracts with Atkinson and Lozano Smith
need not include estimates of the Project’s energy savings.
B. The District’s Contract with Trane Complied with
Section 26206(d).
Section 26206(d) requires that a contract “identify” a project’s
“projected energy savings.” Neither the statute nor the Guidelines
provide any guidance on how an LEA must satisfy this
-A9-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
requirement. For example, neither expressly requires this
projection to be expressed as a dollar figure. As a result, LEAs were
left with reasonable discretion to attempt to identify expected
savings in good faith.
Here, the District’s contract with Trane (“Contract”) does, in fact,
identify the Project’s projected energy savings, although not in a
specific dollar amount. Section 6 of the Contract states as follows:
Anticipated Savings. As required under SB 73, the
District anticipates savings on energy expenditures to
result from the Project in the amount determined by the
approved CEC expenditure plan, over the life cycle of the
Project. That anticipated sum exceeds the Total System
Price by a ratio of at least 1.01.
The Contract identifies the District’s anticipated energy savings in
terms of a savings-to-investment ratio (“SIR”), which is recognized
in the Guidelines as a measure of cost-effectiveness that is explicitly
sanctioned by the CEC. (See Guidelines, p. 23 [“An eligible energy
project must achieve a minimum savings-to-investment ratio (SIR)
of 1.01 to be approved for a Proposition 39 award.”].)….
Section 6 of the Contract states that the Project will yield an SIR of
at least 1.01. The Contract indicates that the Project price is
$3,340,934; so, by multiplying this number by 1.01, one can
reasonably understand from the face of the Contract that the
District’s anticipated savings are at least $3,374,343.34. (Contract,
Section 7.)
Additionally, the Contract states that the anticipated energy savings
would be “in the amount determined by the approved CEC
expenditure plan.” (Contract, Section 6.)
The District could not articulate its anticipated savings with greater
specificity at the time of contracting. Due to the structure of the
Prop 39 program, the savings was based on the scope of work that
could be accomplished. The scope of work in turn affected the
contract price, and contract price was based on Prop 39 funding
amount. In addition to identify the anticipated savings in Section 6,
the parties accounted for this potential change in contract price in
Section 7 of the Contract….
The parties were cognizant of the fact that the District’s EEP had
not yet been approved and that the Contract’s scope of work could
change as a function of the District’s Proposition 39 allocations.
Thus, the parties did not finalize the scope of work at the time of
contracting. Accordingly, the District could not describe its
anticipated energy savings in more specific terms, as the District did
not yet know what energy efficiency measures would be
implemented.
The District’s submitted EEP thereafter described the Project’s
estimated energy savings in great detail. Specifically, the District
presented its projected energy savings in terms of: (1) demand
savings, measured in kilowatts; (2) annual electric savings,
measured in kilowatt hours; and (3) annual cost savings, measured
in dollars. The District thereby reported its anticipated savings to the
CEC.
-A10-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
In sum, the Contract identified the District’s projected energy savings in
terms of: (1) an SIR, which is a savings measurement that has been
explicitly adopted by the CEC; and (2) the information presented in the
District’s EEP, which was reviewed and approved by the CEC. Since
neither the relevant statutes nor the Guidelines establish that a contract
must identify projected savings via any particular method or
measurement, the method used by the District here substantially
complied with the projected energy savings requirement.
It is evident that the District made a good faith effort to strictly and
substantially comply with the requirements of Proposition 39 and did so
to the greatest extent possible.
The district’s response to the Observation is as follows:
The SCO has received information from CDE regarding the specific
amounts provided to [Antelope Valley Union High School District] for
Prop 39 projects, and those funds have been fully accounted for by the
SCO.
During the course of construction, it was found that the initial contractor
did not comply specifically with the Architect’s original drawings for the
installation of the many air conditioning units. The District was required
to issue a change order for those services. These costs were not part of
the original EEP approved by the Energy Commission and therefore
became an added cost to the District. It appears funds may have been
transferred into Resource 62300.0 to cover the impending change order.
The net change order was finalized at $187,452, but was not paid from
Resource 62300.0.
Resource 62300.0 currently has a balance of $37,998.23, which is the
initial amount the District accounted for as the difference between EEP
funds received and expended. Those funds now reside in Object
code 9520 to provide for reimbursement to the CDE. These are the only
funds in Resource code 62300.0 at this time.
SCO Comment
Our findings and recommendations remain unchanged. We will address
the district’s response in the order presented.
Sole-sourced project costs
The district’s response indicates its reliance on the provisions of
Government Code section 53060, PRC section 25620.5(e), the “best
value” provisions of Public Contract Code section 20133(c), and its own
procurement policies and procedures. The district cites its compliance with
these sources as a valid reason for not complying with the sole-source
language of PRC section 26235(c).
The district is correct that the CEC’s Proposition 39 “Frequently Asked
Questions” document1 states:
The LEA shall defer to [its] own procurement regulations and procedures, as
long as they reflect applicable state and local laws and regulations, and do
not conflict with the minimum legal standards specified above.
1 Available under the “Program Information” tab on the “California Clean Energy Jobs Act K-12 Program – Prop 39”
page of the CEC’s website. The quoted text is in the second paragraph on page 27.
-A11-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
In addition, the CEC’s 2016 Program Implementation Guidelines
(“Energy Project Construction Compliance Requirements,” page 35) state:
….The guidelines defer to the LEA’s own procurement regulations and
procedures, as long as they reflect applicable state and local laws and
regulations, and do not conflict with the minimum legal standards specified
above.
However, the district fails to recognize that the guidelines defer to the
LEA’s own procurement regulations as long as they “do not conflict with
the minimum legal standards specified above” [emphasis added].
The “minimum legal standards specified above” are PRC
sections 26206(d), 26235(a)(2), and 26235(c). The district’s procurement
regulations conflict with the sole-source prohibition contained in PRC
section 26235(c); therefore, we found that the district’s reliance on
Government Code section 53060, PRC section 25620.5(e), the “best
value” provisions of Public Contract Code section 20133(c), and its own
policies and procedures in lieu of PRC section 26235(c) was misplaced.
Furthermore, the California State Legislature repealed the “best value”
provisions of PCC section 20133(c) in 2014. As a result, this statute was
not applicable when the district entered into these contracts with its
vendors.
The district’s response includes a legal theory of sole-sourcing that is
based on PRC section 25620.5(e). We are not qualified to opine on the
validity of legal arguments. The district may choose to pursue an appeal
of the audit findings. We provide guidance on filing an appeal elsewhere
in this report.
The district’s response conveys the district’s belief that legal services
related to the Proposition 39 Program do not constitute a “project” under
the provisions of the Program and, therefore, no contract is required. We
disagree. To the extent that a vendor provides legal services to the district
for its Proposition 39 projects, those expenditures constitute part of the
overall project(s)—similar to engineering, inspection, and other “soft”
costs. Accordingly, the district should support program costs for legal
services with a properly executed contract.
No projected energy savings identified
The district states that the program guidelines provide no clear guidance
on how districts can comply with the provisions of PRC section 26206(d).
We disagree. The CEC Proposition 39 Implementation Guidelines state,
“All contracts need a clear and accurate description of the energy project,
including material, products, or services to be procured, and a budget that
includes cost and an estimate of the projected energy savings” [emphasis
added]. The program’s provisions require only an estimate of the projected
energy savings. In addition, no financial impacts apply to districts for
violations of this program provision.
-A12-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
In addition, the district states that it does not need to include projected
energy savings in a contract with its legal counsel. Our finding does not
recommend that the district include projected energy saving in its contract
for legal counsel; rather, our finding identifies the district’s lack of a
signed contract.
Unused planning funds
We found that the district received Proposition 39 Program allocations
from the CDE totaling $5,171,346. The district’s two EEPs contained
approved program costs totaling $5,124,973. We reported the difference
of $46,373 to the CDE as unused planning funds that should be repaid to
the Clean Energy Job Creation Fund.
The district’s accounting records for the Proposition 39 Program include
$189,102 of additional revenue postings that do not indicate the source of
the funds. We advised the district of the need to provide documentation to
substantiate that these funds did not originate from the Proposition 39
Program. The district did not provide such documentation.
-A13-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Children of Promise Preparatory Academy
Proposition 39 Program
Background The CEC approved Children of Promise Preparatory Academy’s EEP for
$267,668, consisting of $21,538 for energy management services, $4,308
for training, and $241,822 for program implementation. The charter school
used its program implementation funds for the following energy efficiency
measures:
Proposition 39 Reported
Share Used at Energy Annual Cost
School Site School Site Efficiency Measures* Savings
Children of Promise Interior/exterior lighting retrofit, lighting controls, and
Preparatory Academy $ 241,822 HVAC-Packaged/Split System AC/Heat Pump/VRF $ 11,009
*HVAC: Heating, venting, and air conditioning; AC: air conditioning; VRF: variable refrigerant flow
With these energy efficiency measures, the charter school reported a
combined SIR of 1.05 and the creation of 1.35 direct job-years.
We audited Proposition 39 program costs to ensure compliance with the
Audit Results
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Sole-sourced project costs
The charter school sole-sourced its contract with First Note Finance, Inc.
($26,533) for its energy manager services. The charter school did not
provide supporting documentation to show that it considered other
vendors before awarding its contract to First Note Finance, Inc. Therefore,
we found that the charter school sole-sourced this Proposition 39 contract,
totaling $26,533.
However, the charter school requested only $25,846 in its EEP, for an
energy manager and training costs. Because we audited only the amount
approved in the charter school’s final project completion report, we found
that the charter school sole-sourced a total of $25,846.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”
PUC section 388(b) states:
The Department of General Services or any other state or local agency
intending to enter into an energy savings contract or a contract for an
energy retrofit project may establish a pool of qualified energy service
companies based on qualifications, experience, pricing, or other
pertinent factors. Energy service contracts for individual projects
undertaken by any state or local agency may be awarded through a
-A14-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
competitive selection process to individuals or firms identified in the
pool. The pool of qualified energy service companies and contractors
shall be reestablished at least every two years or shall expire.
No projected energy savings identified and/or no signed contract
We reviewed the charter school’s contracts with Stinson Mechanical
Contractors, and Felix Electrical and Construction Service, and
determined that the contracts do not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Violation of energy measure payback period
The charter school closed on June 30, 2020 after Inglewood Unified
School District denied the school’s charter petition. The facility is
currently vacant and for sale as a charter school site. The school completed
its energy projects in 2018 using $241,822 of Proposition 39 funds with
energy payback periods of seven years for its lighting project and
27.7 years for its HVAC system project. Until this facility is sold, the
charter school is in violation of the energy measure payback period.
Per the CEC’s 2016 Program Implementation Guidelines (“Step 8: Energy
Project Tracking and Reporting,” page 33), “LEAs must not sell or
demolish the approved energy measure installed with Proposition 39
program award funding prior to the payback of the energy measure.”
PRC section 26235(i) states, “…an LEA receiving moneys pursuant to this
chapter for a project for that facility shall require that the school repay to
the state all moneys received from the Job Creation Fund for the project if
the school voluntarily vacates the facility within five years of project
completion.…”
Recommendation
We recommend that:
The CDE take appropriate action to recover Proposition 39 funds that
the district expended on sole-sourced project costs, in violation of
PRC section 26235(c); and
The CEC monitor the sale of the Children of Promise Preparatory
Academy facility to ensure that they will continue being used as a
school site.
No additional recommendation is applicable, as the Proposition 39
program has ended.
Charter School’s Response
We informed the charter school of the audit findings via email on May 4,
2021. Carleton Lincoln, Ed.D., Founder/CEO, responded by letter dated
June 4, 2021. The charter school’s response letter is included as
Attachment B.
-A15-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The charter school’s response to our audit findings is as follows:
COPPA [Children of Promise Preparatory Academy] was forced to close
in June 2020 due to Inglewood Unified School District’s (IUSD)
unwarranted denial of COPPA’s charter petition. This closure happened
before the State Controller’s Office initiated the audit on September 28,
2020.
Because of the closure, COPPA had no staff, no paid hours, no facility,
and no resources to locate and provide answers and supporting
documents to the auditor. The few resources that COPPA did have was
used for the wind-down and dissolution of the school as required by state
and federal law. In addition, all of the school’s documents were archived
in long term storage with no intent to be in active use. Former staff that
had knowledge about where and how the records were stored and
organized were no longer employed.
Moreover, the school was impacted by COVID-19, an unprecedented
event and global in nature. Access to physical storage and to former
contractors and organizations related to Prop 39 was severely limited.
In the month of May 2021, most of COPPA’s activities had to be
suspended due [to] Dr. Carleton Lincoln’s, the CEO’s, medical
emergency. Dr. Lincoln makes up the majority of the school’s staff.
At the end of May, COPPA received a court order for the appointment
of a receiver who is to marshal and dispose of the school property and
school’s assets. This means that COPPA will no longer have any
resources, including Dr. Lincoln and his assistant, to even wind down
and dissolve the school and there will be no one at COPPA to continue
correspondence with your office.
The school has attempted to cooperate and provide what little
documentation could be provided, despite the school’s closure and
discontinued operation months before the audit.
We are concerned that the audit findings are unreasonable because a
closed school that is no longer in operation cannot realistically provide
adequate answers. It seems that auditing a closed school would
inevitably conclude with negative findings because the school could not
proffer an appropriate response.
COPPA respectfully ask the auditor to reconsider and dismiss their
findings and/or forgive any penalties assessed against the school due to
the extraordinary impact of COVID-19 and the unfortunate and
unwarranted closing of the school.
SCO Comment
Our findings and recommendation remain unchanged.
Although we recognize that the charter school participated in the program
to the best of its ability, the scope of our audit is to ensure compliance with
state statutes and regulations. These requirements state, in part, that LEAs
cannot use a sole-source process to award funds for energy management
services, and that LEAs must identify projected energy savings in the
awarded contracts.
SCO provides audit services for the Citizens Oversight Board related to
the Proposition 39 Program, but does not have authority to dismiss and/or
forgive related audit findings and/or penalties assessed against the school.
-A16-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Coast Unified School District
Proposition 39 Program
Background The CEC approved Coast Unified School District’s EEP for $224,784,
consisting of $1,983 for energy management services and $222,801 for
program implementation. The district used its program implementation
funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures* Savings
Cambria Grammar $ 16,686 Exterior lighting retrofit $ 2,501
Coast US District Office 34,148 Interior/exterior lighting retrofit; HVAC controls; HVAC-Condensing furnace 1,647
Coast Union High 95,302 Interior/exterior lighting retrofit; HVAC controls; HVAC-Condensing furnace 7,645
Leffingwell High 7 ,093 Exterior lighting retrofit; HVAC controls 5 14
HVAC-condensing furnace; HVAC controls; interior/exterior lighting retrofit;
Santa Lucia Middle 69,572 HVAC-Packaged/split system AC/Heat Pump/VRF 4,773
Total $ 222,801 $ 1 7,080
*HVAC: Heating, ventilation, and air conditioning; AC: air conditioning; VRF: variable refrigerant flow
With these energy efficiency measures, the district reported a combined
SIR of 1.39 and the creation of 1.25 direct job-years.
In addition, the district received $57,272 in planning funds directly from
the CDE, which it used for an energy manager.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
No projected energy savings identified and/or no signed contract
We reviewed the district’s contracts with JR Barto (HVAC) and Energy
Retrofit Co. (lighting), and determined that the contracts do not identify
the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion report submitted late
The district’s final report was submitted on March 13, 2020, 31 months
after the reported project completion date of September 21, 2017.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
-A17-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
District’s Response
We informed the district of the audit findings via email on March 3, 2021.
Annie Lachance, Chief Business Official, responded via email on
March 11, 2021.
The district’s response to Finding 5 – No projected energy savings
identified and/or no signed contract, is as follows:
All projected energy savings was included in the studies done prior to
the contracts. The projected energy savings was not included as part of
the contract.
The district’s response to Finding 6 – Final project completion report
submitted late, is as follows:
Per CEC reporting process, the “Final Report” is generated based on
the completion status of the “Annual Progress Report.” After
reviewing the timeline, it appears [that] the completion status in the
2018 “Annual Progress Report” (APR) was mistakenly checked as
“NOT Completed.” This error was corrected in 2019 Annual
Progress Report, but unfortunately it put us 12 months behind.
We indicated the completion status as complete in the 2019 Annual
Progress Report and were awaiting the release of the Final Report
around October, 2019. After waiting for several months for the
FINAL REPORT, we contacted CEC in December 2019. We began
working with the project manager in January, 2020 to complete an
amendment, then we received the FINAL REPORT in February,
2020. Please note that both CEC and CLEAResult’s operations (IT
and management support) were severely challenged by COVID 19
related “Shelter-in-Place” order but we were able to get the Final
Report released in February and completed in March of 2020. This
set us back a few months as well.
SCO Comment
Our findings remain unchanged.
Although we recognize that the district participated in the program to the
best of its ability, the scope of our audit is to ensure compliance with state
statutes and regulations, which require that the projected energy savings
be identified in the awarded contract.
-A18-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Community Collaborative Charter School
Proposition 39 Program
Background The CEC approved Community Collaborative Charter School’s EEP for
$197,200. The charter school used its program implementation funds for
the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures* Savings
Community Collaborative Charter $ 197,200 Interior/exterior lighting retrofit; HVAC controls $ 9,687
*HVAC: Heating, ventilation, and air conditioning
With these energy efficiency measures, the charter school reported a
combined SIR of 1.05 and the creation of 1.10 direct job-years.
In addition, the charter school received $114,500 in planning funds
directly from the CDE, which it used for screening and audits, and
program assistance.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
No projected energy savings identified and/or no signed contract
We reviewed the district’s contract with Alliance Building Solutions, and
determined that the contract does not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion report submitted late
The district’s final report was submitted on November 26, 2019,
23 months after the reported project completion date of December 17,
2017.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
-A19-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Charter School’s Response
We informed the charter school of the audit findings via email on
March 19, 2021. The school responded later that day requesting a formal
exit conference. We conducted a formal telephone exit conference with
the school representatives on March 25, 2021. Aaron Thornsberry, Chief
Business Official, responded via email later that day agreeing with the
audit findings.
The charter school’s response to Finding 5 − No projected energy savings
and/or no signed contract, is as follows:
We agree with the State Controller’s Office finding in accordance with
section 26206(d). Projected energy savings were not included in the
contract, but [were] shared with us outside of the contract to ensure the
contract scope was appropriate. This was an oversight by our
organization.
The charter school’s response to Finding 6 – Final project completion
report submitted late, is as follows:
We agree with the State Controller’s Office Finding in accordance with
section 26240(b). Unfortunately, we could not file timely as the data
needed to file the report was delayed from the utility companies and was
not received until well after the deadline. The report was submitted as
quickly as possible after receiving the data.
-A20-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Cotati Rohnert Park Unified School District
–
Proposition 39 Program
Background The CEC approved Cotati–Rohnert Park Unified School District’s
EEP Number 4951 for $1,055,335, consisting of $103,004 for energy
management services and $952,331 for program implementation. In
addition, the CEC approved the district’s EEP Number 5126 for $135,400,
consisting of $10,000 for energy management services and $125,400 for
program implementation. The district used its program implementation
funds for the following efficiency measures:
Proposition 39 Energy Efficiency and Reported
Share Used Renewable Energy Annual Cost
School Site at School Site Generation Measures* Savings
EEP #4951:
HVAC Controls−Programmable/Smart Thermostats; HVAC−
Evergreen Elementary $ 250,176 Packaged/split system AC/heat pump/VRF; HVAC−Duct sealing $ 9,663
John Reed Primary 110,632 Interior/exterior lighting retrofit; interior linear fluorescent relamping 9,286
Rancho Cotati HS 379,879 Interior/exterior lighting retrofit; interior linear fluorescent relamping 38,868
Thomas Page Academy 9 9,809 Interior/exterior lighting retrofit; interior linear fluorescent relamping 9,935
Waldo Rohnert Intermediate 111,835 Interior/exterior lighting retrofit; interior linear fluorescent relamping 8,471
Total, EEP #4951 $ 952,331 $ 7 6,223
EEP #5126:
Technology High $ 125,400 HVAC−Chiller/boiler replacement $ 1,936
Total, EEP #5126 $ 125,400 $ 1,936
*HVAC: Heating, venting, and air conditioning; AC: air conditioning; VRF: variable refrigerant flow
With the energy efficiency measures from EEP Number 4951, the district
reported a combined SIR of 1.46 and the creation of 5.33 direct job-years.
With the energy efficiency measures from EEP Number 5126, the district
reported a combined SIR of 1.01 and the creation of 0.70 direct job-years.
In addition, the district received $130,000 in planning funds directly from
the CDE, which it used for screening and audits, and an energy manager.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
No projected energy savings identified and/or no signed contract
We reviewed the district’s contract with Indoor Environmental Services
(IES), and determined that the contract does not identify the projected
energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
-A21-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Final project completion report submitted late
The district’s final report for EEP Number 4951 was submitted on
December 3, 2019, 61 months after the reported project completion date
of November 1, 2014. The district’s final report for EEP Number 5126
was submitted on December 3, 2019, 16 months after the reported project
completion date of August 31, 2018.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
District’s Response
We informed the district of the two audit findings on March 2, 2021.
Robert Marical, Chief Business Official, responded via email on March 8,
2021.
The district’s response to Finding 5 – No projected energy savings
identified and/or no signed contract, is as follows:
The District included the projected energy savings as an attachment to
the Board Resolution that was approved by the Board. Additionally,
energy savings calculations were performed with the help of the on-line
Energy Saving Calculators developed by California Energy Commission
(CEC). These on-line calculators are offered by CEC as a part of
Proposition 39 program. The projected savings were then submitted as
part of the process and approved by the CEC. All documents were
approved as part of the project. We think the District acted within the
spirit and guidelines of the program. We will include projected savings
in future contracts moving forward.
The district’s response to Finding 6 – Final project completion report
submitted late, is as follows:
Our contractor reported that there was an issue gathering data from
PG&E in a timely manner, which caused delays in completing the Final
Reports for EEP 5126 within the 15 month timeframe. They were
submitted a few weeks after the deadline. Final Reports from EEP 4951
also had data retrieval issues after the amendment was approved.
SCO Comment
Our findings remain unchanged.
Although we recognize that the district participated in the program to the
best of its ability, the scope of our audit is to ensure compliance with state
statutes and regulations, which require that the projected energy savings
be identified in the awarded contract.
-A22-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Desert Sands Unified School District
Proposition 39 Program
Background The CEC approved Desert Sands Unified School District’s EEP for
$6,521,118. The district used its program implementation funds for the
following energy efficiency measures and renewable energy generation
measures:
Proposition 39 Energy Efficiency and Reported
Share Used Renewable Energy Annual Cost
School Site at School Site Generation Measures* Savings
Indio Middle $ 566,865 Interior/exterior lighting fixture retrofit $ 3 5,093
La Quinta High 1 ,100,932 HVAC-Packaged/Split System AC/Heat Pump/VRF 62,818
La Quinta Middle 560,657 Interior/exterior lighting fixture retrofit 32,210
Madison Elementary 281,749 Interior/exterior lighting fixture retrofit 18,067
Monroe Elementary 278,540 Interior/exterior lighting fixture retrofit 16,185
Palm Desert High 3 ,329,610 Photovoltaic panels 2 41,308
Truman Elementary 402,765 Interior/exterior lighting fixture retrofit 24,306
Total $ 6,521,118 $ 429,987
*HVAC: Heating, ventilation, and air conditioning; AC: air conditioning; VRF: variable refrigerant flow
With these energy efficiency and renewable energy generation measures,
the district reported a combined SIR of 1.03 and the creation of
31.85 direct job-years.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issue:
Final project completion report submitted late
The district’s final report was submitted on May 10, 2019, 52 months after
the reported project completion date of December 31, 2014.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
-A23-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
District’s Response
We informed the district of the audit finding via email on March 11, 2021.
Sonya Melendez, Director of Fiscal Services, responded via email on
March 22, 2021.
The district’s response to the finding is as follows:
Due to turnover in key positions overseeing this project, there was an
oversight on the timely submission of the report of project expenditures
to the Citizens Oversight Board. Once this was brought to the District’s
attention, the report was submitted.
SCO Comment
Our finding remains unchanged.
-A24-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Madera Unified School District
Proposition 39 Program
Background The CEC approved Madera Unified School District’s EEP for $4,790,235,
consisting of $331,843 for energy management services, $66,368 for
training, and $4,392,024 for program implementation. The district used its
program implementation funds for the following energy efficiency
measures:
Proposition 39 Reported
Share Used at Energy Annual Cost
School Site School Site Efficiency Measures* Savings
Alpha Elementary $ 32,839 Exterior lighting fixture retrofit, HVAC controls $ 3,359
Berenda Elementary 1 5,908 Exterior lighting fixture retrofit, HVAC controls 2,587
Cesar Chavez Elementary 5 3,054 Exterior lighting fixture retrofit, HVAC controls 3,482
District Office Maintenance, Transportation 6 0,728 Exterior lighting fixture retrofit, HVAC controls 7,234
Dixieland Elementary 5,616 Exterior lighting fixture retrofit, HVAC controls 1,280
Eastin Arcola 8,200 Exterior lighting fixture retrofit, HVAC controls 2,138
Furman (Duane E.) High** 1 4,926 Exterior lighting fixture retrofit, HVAC controls 1,300
George Washington Elementary 9,092 Exterior lighting fixture retrofit, HVAC controls 1,768
Howard Elementary 1 3,977 Exterior lighting fixture retrofit, HVAC controls 1,921
Jack G. Desmond Middle 9 8,261 Exterior lighting fixture retrofit, HVAC controls 9,730
James Madison Elementary 1 3,523 Exterior lighting fixture retrofit, HVAC controls 1,929
James Monroe Elementary 9,538 Exterior lighting fixture retrofit, HVAC controls 1,627
John Adams Elementary 9,043 Exterior lighting fixture retrofit, HVAC controls 1,544
John J. Pershing Elementary 2 1,583 Exterior lighting fixture retrofit, HVAC controls 2,778
La Vina Elementary 1 2,734 Exterior lighting fixture retrofit, HVAC controls 1,874
Exterior lighting fixture retrofit, HVAC controls;
Lincoln Elementary 286,975 HVAC controls−EMS 19,248
Madera High 164,866 Interior/exterior lighting fixture retrofit; HVAC controls 15,228
Interior/exterior lighting fixture retrofit; HVAC controls;
HVAC−chiller/boiler replacement; HVAC controls−
Madera South High 1,667,751 EMS; Pumps, motors, drives 77,066
Interior/exterior lighting fixture retrofit; HVAC controls;
HVAC−chiller/boiler replacement; HVAC−packaged/ split
Martin Luther King Jr. Middle 1,756,732 system AC/heat pump/VRF 41,197
Millview Elementary 9,983 Exterior lighting fixture retrofit, HVAC controls 1,739
Nishimoto Elementary 3 2,837 Exterior lighting fixture retrofit, HVAC controls 3,148
Parkwood Elementary 3 3,386 Exterior lighting fixture retrofit, HVAC controls 3,458
Ripperdan Community Day 3,178 HVAC controls 1,081
Sierra Vista Elementary 1 0,035 Exterior lighting fixture retrofit, HVAC controls 1,679
Thomas Jefferson Middle 4 7,259 Interior/exterior lighting fixture retrofit; HVAC controls 5,342
Total $ 4 ,392,024 $ 2 13,737
*HVAC: Heating, ventilation, and air conditioning; EMS: emergency medical services (fire alarms); AC: air conditioning;
VRF: variable refrigerant flow
**Independent Study
With these energy efficiency measures, the district reported a combined
SIR of 1.10 and the creation of 24.60 direct job-years.
In addition, the district received $292,039 in planning funds directly from
the CDE, which it used for screening and audits, and program assistance.
-A25-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Sole-sourced project costs
The district contracted with the following vendors:
ThinkWire Energy Services − $12,395 for solar consulting services;
US Air Conditioning Distributors − $165,719 for thermostats;
Knorr Systems − $32,581 for a pool pump control; and
Cenergistic − $129,246 for an energy conservation program.
The district did not provide supporting documentation to show that it
considered other vendors before awarding contracts to ThinkWire Energy
Services, US Air Conditioning Distributors, Knorr Systems, and
Cenergistic. Therefore, we found that the district sole-sourced these
Proposition 39 contracts, totaling $339,941.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”.
PUC section 388(b) states:
The Department of General Services or any other state or local agency
intending to enter into an energy savings contract or a contract for an
energy retrofit project may establish a pool of qualified energy service
companies based on qualifications, experience, pricing, or other
pertinent factors. Energy service contracts for individual projects
undertaken by any state or local agency may be awarded through a
competitive selection process to individuals or firms identified in the
pool. The pool of qualified energy service companies and contractors
shall be reestablished at least every two years or shall expire.
No projected energy savings identified and/or no signed contracts
We reviewed the district’s supporting documentation and determined that
no contract was prepared for the services provided by Knorr Systems.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion report submitted late
The district’s final report was submitted on September 4, 2019, 22 months
after the reported project completion date of November 30, 2017.
-A26-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
We recommend that the CDE take appropriate action to recover
Proposition 39 funds that the district expended on sole-sourced project
costs, in violation of PRC section 26235(c).
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit findings and Observation via email
on February 1, 2021. Sandon Schwartz, Deputy Superintendent, responded
by letter dated February 10, 2021. The district’s response letter is included
as Attachment C.
The district’s response to Finding 1 – Sole-sourced project costs, is as
follows:
The District feels they complied with the spirit of sole-sourcing and in
the case of the thermostats received multiple quotes from vendors before
purchasing with the lower priced vendor.
Think Wire − The courts have noted that the Legislature has recognized
the right to hire certain special services without competitive bidding by
enacting Government Code section 53060. In this case, the District
selected Think Wire to conduct a solar analysis based on this government
code.
US Air Conditioning Distributors − As the energy projects were initiated
in phases over several years, the district purchased the thermostats over
a wide time frame to meet scope of the various phases. The thermostats
were purchased over a two-year period following appropriate and
acceptable procurement procedures. The district did not competitively
bid these [thermostats] but received pricing from multiple vendors prior
to initiating the first purchase order in February of 2017. These
additional quotes are included as backup on the purchase requisitions.
These thermostats provided the district a best value based on pricing and
allowed the district to have a consistent wi-fi thermostat that could
enable a functioning EMS system on a single platform throughout the
district, promoting efficiency.
Knorr Systems − The district purchased the VFD [variable-frequency
drive]-based pool controls system for Madera South High School, as part
of the Prop 39 project, from Knorr Systems. Since the cost of the product
was below the bid threshold limit, the district did not receive multiple
bids.
-A27-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Cenergistic − The district contracted with Cenergistic in 2015 to provide
energy management services. Cenergistic then hired a district employee
to serve as the energy manager. The contract guaranteed savings and if
contract costs exceeded savings, then the district would be refunded
those costs. No other consultant would offer those [terms]. The district
hired Cenergistic on a best-value basis using Government Code
section 53060. The consultant was not originally funded using Prop 39
funding. The district shifted some of these expenses to our Prop 39
program in the final year of the funding cycle.
The district did not respond to Finding 5 – No projected energy savings
identified and/or no signed contract.
The district’s response to Finding 6 – Final project completion report
submitted late, is as follows:
The district acknowledges and accepts this finding. Final reporting was
part of the scope of the contract with IES. IES stated to the district that
the report was filed late due to their ability to obtain utility data from
PG&E. PG&E had changed nearly all of the meter numbers and IES was
having difficulties retrieving several meters’ data even with PG&E’s
help. IES ended up using one of their software programs to directly
retrieve the data for us through PG&E’s servers. This setup process took
longer than expected but did provide the utility information they were
unable to obtain in any other manner.
SCO Comment
Our findings and recommendation remain unchanged.
The scope of our audit was to ensure compliance with state statutes and
regulations. Although the district cites using the “best value” criteria as
defined in Government Code section 53060 to support its use of sole-
sourced contracts, PRC section 26235(c) states:
A community college district or LEA shall not use a sole source process
to award funds pursuant to this chapter. A community college or LEA
may use the best value criteria as defined in paragraph (1) of
subdivision (c) of Section 20133 of the Public Contract Code to award
funds pursuant to this chapter [emphasis added].
The CEC’s Proposition 39 “Frequently Asked Questions” document2
defines the “best value” criteria as follows:
In 2014, Section 20133 of the Public Contract Code was repealed and
amended. The legislation that repealed Section 20133 also added a new
statute to the Public Contract Code containing a more precise definition of
“best value” (Pub. Contract Code §21161). That definition has been refined
several times, and the LEA should refer to the current language of
Section 21161 for guidance on use of the best value criteria.
2Available under the “Program Information” tab on the “California Clean Energy Jobs Act K-12 Program – Prop 39”
page of the CEC’s website. The quoted text is in the first paragraph of page 27.
-A28-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PCC section 21161 states, in part, “All contracts shall be let to the lowest
responsible bidder or bidders in the manner provided in this article.”
The district provided two additional quotes for the thermostats ultimately
purchased from US Air Conditioning Distributors. However, the district
did not identify the vendor’s name for either quote; nor did it provide
documentation to show when these quotes were obtained or printed.
In its response, the district indicates its reliance on the provisions of
Government Code section 53060, and its own procurement policies and
procedures. The district cites its compliance with these sources as a valid
reason for not complying with the sole-source language of PRC
section 26235(c).
However, the CEC’s Proposition 39 Implementation Guidelines state that
“the guidelines defer to the LEA’s own procurement regulations and
procedures, as long as they reflect applicable state and local laws and
regulations and do not conflict with the minimum legal standards specified
above” [emphasis added]. The “minimum legal standards specified above”
are PRC sections 26206(d), 26235(a)(2), and 26235(c). Therefore, we
found that the district’s reliance on Government Code section 53060 and
its own policies and procedures in lieu of PRC section 26235(c) was
misplaced.
-A29-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Mattole Valley Charter School
(Mattole Unified School District)
Proposition 39 Program
The CEC approved Mattole Valley Charter School’s EEP for $168,197.
Background
The charter school used its program implementation funds for the
following energy efficiency and renewable energy generation measures:
Proposition 39 Energy Efficiency and Reported
Share Used Renewable Energy Annual Cost
School Site at School Site Generation Measures* Savings
Beginnings Learning Center $ 44,935 Photovoltaic (solar) $ 2,138
Campus House 3 ,014 Interior lighting fixture retrofit 1 99
Caspar Creem Learning Center 33,025 Interior lighting fixture retrofit; HVAC–Packaged 6 66
Creekside Learning Center 18,000 Photovoltaic (solar) 1,668
Diamond View Mattole Learning Center 27,189 Interior lighting fixture retrofit; HVAC–Split system AC/heat pump 5,734
Lost Coast High Learning Center 6 ,337 Interior/exterior lighting fixture retrofit 1,962
Mattole Valley Charter-Registrar 3 ,536 Interior/exterior lighting fixture retrofit 3 80
North Coast Learning Academy 24,511 Interior/exterior lighting fixture retrofit 3,066
Resource Center 7 ,650 Interior lighting fixture retrofit 1,672
Total $ 168,197 $ 1 7,485
*HVAC: Heating, ventilation, and air conditioning; AC: air conditioning
With these energy efficiency and renewable energy generation measures,
the district reported a combined SIR of 1.75 and the creation of 0.85 direct
job-years.
In addition, the district received $51,717 in planning funds directly from
the CDE, which it used for program assistance and an energy manager.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Unspent funds
The charter school was awarded $51,717 in planning funds and $225,776
in implementation funds. Of those two amounts, the charter school used
only $26,362 and $168,198, respectively. Therefore, the charter school has
a total of $82,933 ($25,355 for planning and $57,578 for program
implementation) in unspent funds.
On February 2, 2021, we notified CDE of the unspent funds. Prior to
issuance of this report, CDE followed up with the Humboldt County
Office of Education to recover the unspent funds from Mattole Valley
Charter School.
The CEC’s 2016 Program Implementation Guidelines state on page 5:
The SSPI [State Superintendent of Public Instruction] is responsible for
administering awards to LEAs that serve grades K-12 students. These
funds may be used by LEAs for energy efficiency and clean energy
-A30-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
projects, related energy planning, energy training, energy management,
and energy projects with related non-energy benefits. LEAs are required
to submit an energy expenditure plan to the Energy Commission for
consideration and approval. Funds are released to the LEA only after the
Commission approves an LEA’s energy expenditure plan(s).
PRC section 26240(b) states, “As a condition of receiving funds from
the Job Creation Fund…the entity shall submit a report of its project
expenditures to the Citizens Oversight Board.…”
PRC section 26240(h)(1) states, “The Superintendent of Public
Instruction shall require local educational agencies to pay back funds
if they are not used in accordance with state statute or regulations....”
Final project completion report submitted late
The charter school’s final report was submitted on March 13, 2020,
21 months after the reported project completion date of June 30, 2018.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
We recommend that the district return the unspent funds to the State.
Although the Proposition 39 program has ended, the unspent funds must
be returned.
No additional recommendation is applicable, as the Proposition 39
program has ended.
Charter School’s Response
We informed the charter school of the audit findings via email on
January 25, 2021. Shari Lovett, Director, Northern United−Humboldt
Charter School (formerly the Director of Mattole Valley Charter School),
responded via email on February 8, 2021, stating that Karen Ashmore,
Superintendent, Mattole Unified School District, will not be providing a
response.
-A31-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Modesto City Elementary School District
Proposition 39 Program
The CEC approved Modesto City Elementary School District’s EEP for
Background
$3,707,593. The district used its program implementation funds for the
following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Alberta Martone Elementary $ 272,561 Interior/exterior lighting fixture retrofit $ 1 4,373
Bret Harte Elementary 62,701 Exterior lighting fixture retrofit 3,290
Burbank Elementary 29,461 Exterior lighting fixture retrofit 1,303
Catherine Everett Elementary 234,288 Interior/exterior lighting fixture retrofit; lighting controls 12,730
District Nutrition Services 147,379 Interior/exterior lighting fixture retrofit 11,941
El Vista Elementary 239,460 Interior/exterior lighting fixture retrofit 12,477
Elihu Beard Elementary 249,007 Interior/exterior lighting fixture retrofit 10,970
Enslen Elementary 190,593 Interior/exterior lighting fixture retrofit 8,920
Evelyn Hansahw Middle 74,342 Exterior lighting fixture retrofit; lighting controls 4,209
Fairview Elementary 42,267 Exterior lighting fixture retrofit 2,414
Franklin Elementary 22,998 Exterior lighting fixture retrofit 1,776
Harriette Kirschen Elementary 194,806 Interior/exterior lighting fixture retrofit; lighting controls 10,932
James Marshall Elementary 25,299 Exterior lighting fixture retrofit 1,247
John Fremont Elementary 275,072 Interior/exterior lighting fixture retrofit 14,778
John Muir Elementary 206,940 Interior/exterior lighting fixture retrofit; lighting controls 12,971
La Loma Junior High 37,236 Exterior lighting fixture retrofit; lighting controls 3,050
Lakewood Elementary 14,098 Exterior lighting fixture retrofit 8 90
Mark Twain Junior High 23,359 Exterior lighting fixture retrofit; lighting controls 2,610
Orville Wright Elementary 25,807 Exterior lighting fixture retrofit 1,933
Robertson Road Elementary 9 ,015 Exterior lighting fixture retrofit 7 65
Roosevelt Junior High 362,735 Interior/exterior lighting fixture retrofit; lighting controls 16,507
Rose Avenue Elementary 275,845 Interior/exterior lighting fixture retrofit 13,769
Shackelford Elementary 217,147 Interior/exterior lighting fixture retrofit; lighting controls 10,730
Sonoma Elementary 25,643 Exterior lighting fixture retrofit 1,374
Tuolumne Elementary 19,951 Exterior lighting fixture retrofit 8 79
William Garrison Elementary 275,830 Interior/exterior lighting fixture retrofit 14,221
Wilson Elementary 153,753 Interior/exterior lighting fixture retrofit 7,112
Total $ 3,707,593 $ 198,171
With these energy efficiency measures, the district reported a combined
SIR of 1.06 and the creation of 20.76 direct job-years.
In addition, the district received $230,589 in planning funds directly from
the CDE, which it used for screening and audits.
We audited Proposition 39 program costs to ensure compliance with the
Audit Results
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Unspent earned interest
The district accumulated interest, totaling $22,163, on allocations it
received from the Proposition 39 program. The district’s approved EEP
was completed and the final report was submitted. The district applied all
-A32-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
of its awarded Proposition 39 funds to all projects within its approved EEP.
As the Proposition 39 program has ended and there are no remaining
eligible energy projects on which the district can expend the earned
interest, it should be returned to the Clean Energy Job Creation Fund.
We notified CDE of the unspent earned interest on May 4, 2021. CDE
responded by email on May 4, 2021, stating:
Similar to the way CDE recovers interest on other funds, the district can
send a check referencing the specific program and the funds will be
credited accordingly. So there will not be an invoice. We sent
instructions to Modesto City Elementary on how the district can return
the unused interest earned on Prop 39 funds to CDE and will follow up
with the district to assist with this recovery.
The CEC’s 2016 Program Implementation Guidelines (“Interest Earned
on Proposition 39 Funds,” page 10) state:
Any interest earned on Proposition 39 funds shall be expended only
toward Proposition 39 eligible energy projects. LEAs should make every
effort to track interest earned from Proposition 39 allocations separately
for use on Proposition 39 eligible energy projects and to facilitate
auditing in accordance with PRC 26206(e) and 26240(h)(1).
PRC section 26206(e) states, “All projects shall be subject to audit.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”
Final project completion report submitted late
The district’s final report was submitted on April 8, 2020, 16 months after
the reported project completion date of December 15, 2018.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund… the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
We recommend that the district return the unspent earned interest to the
State. Although the Proposition 39 program has ended, the unspent funds
must be returned.
No additional recommendation is applicable, as the Proposition 39
program has ended.
-A33-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
District’s Response
We informed the district of the audit findings via email on May 4, 2021.
Carole Phipps, Accountant – Capital Funds, responded via email on
May 14, 2021.
The district’s response to Finding 4 – Unspent earned interest, was
“Acknowledged.”
The district’s response to Finding 6 – Final project completion report
submitted late, is as follows:
JCI attempted to retrieve utility information from the Modesto Irrigation
District [MID] for the report; however, due to COVID-19, MID was shut
down temporarily while they reorganized to a work from home model.
Once they were established it took some time to retrieve the numerous
billings associated with the MCSD [Modesto City School District]
project. During that time JCI was corresponding with the CEC Project
Manager about the delay regularly to provide status updates and his
approval.
SCO Comment
Our findings remain unchanged.
-A34-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Mountain Empire Unified School District
Proposition 39 Program
Background The CEC approved Mountain Empire Unified School District’s EEP for
$459,915, consisting of $45,833 for energy management services, $9,167
for training, and $404,915 for program implementation. The district used
its program implementation funds for the following energy efficiency and
renewable energy generation measures:
Proposition 39 Energy Efficiency and Reported
Share Used Renewable Energy Annual Cost
School Site at School Site Generation Measures Savings
Mountain Empire High $ 48,736 Exterior lighting fixture retrofit $ 4,382
Potrero Elementary 356,179 Photovoltaic (solar) 25,498
Total $ 404,915 $ 29,880
With these energy efficiency measures, the district reported a combined
SIR of 1.20 and the creation of 1.77 direct job-years.
In addition, the district received $114,629 in planning funds directly from
the CDE, which it used for screening and audits, an energy manager, and
training.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Sole-sourced project costs
The district sole-sourced its contracts with IES for its energy manager and
training services ($68,750), energy efficiency improvements and
installation of solar systems ($497,175), and facility energy master plan
services ($29,520). The district did not provide supporting documentation
to show that it considered other vendors before awarding these contracts
to IES. Therefore, we found that the district sole-sourced these
Proposition 39 contracts, totaling $595,445.
However, CEC approved only $574,544 for the district’s EEP. Because
we audited only the amount approved by the CEC in the district’s final
project completion report, we found that the district sole-sourced a total
of $574,544.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations…”.
-A35-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PUC section 388(b) states:
The Department of General Services or any other state or local agency
intending to enter into an energy savings contract or a contract for an
energy retrofit project may establish a pool of qualified energy service
companies based on qualifications, experience, pricing, or other
pertinent factors. Energy service contracts for individual projects
undertaken by any state or local agency may be awarded through a
competitive selection process to individuals or firms identified in the
pool. The pool of qualified energy service companies and contractors
shall be reestablished at least every two years or shall expire.
No projected energy savings identified and/or no signed contracts
We reviewed the district’s contract with IES, and determined that the
contract does not identify the projected energy savings. In addition, the
district did not have a signed contract with IES for its facility energy
master plan services.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion report submitted late
The district’s final report was submitted on July 1, 2019, 23 months after
the reported project completion date of July 20, 2017.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
We recommend that the CDE take appropriate action to recover
Proposition 39 funds that the district expended on sole-sourced project
costs, in violation of PRC section 26235(c).
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit findings via email on March 11, 2021.
The district did not respond to the audit findings.
-A36-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Romoland School District
Proposition 39 Program
Background The CEC approved Romoland Elementary School District’s EEP for
$839,484. The district used its program implementation funds for the
following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures* Savings
Boulder Ridge Elementary $ 190,953 Interior lighting retrofit $ 3 0,422
Harvest Valley Elementary 375,467 Interior lighting retrofit; HVAC–Packaged/split system AC/Heat Pump/VRF 34,784
Mesa View Elementary 195,633 Interior lighting retrofit 35,799
Romoland Administration Office 3 3,341 Interior lighting retrofit 3,341
Romoland Elementary 4 4,090 Interior lighting retrofit 19,716
Total $ 839,484 $ 124,062
*HVAC: Heating, ventilation, and air conditioning; AC: air conditioning; VRF: variable refrigerant flow
With these energy efficiency measures, the district reported a combined
SIR of 1.58 and the creation of 4.70 direct job-years.
In addition, the district received $42,400 in planning funds directly from
the CDE, which it used for screening and audits.
We audited Proposition 39 program costs to ensure compliance with the
Audit Results
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issue:
Ineligible expenditures
We reviewed the district’s accounting ledgers and found that it received
and expended $887,962 in Proposition 39 funds However, the district’s
approved EEP, Number 5698, authorized only $881,884 in Proposition 39
expenditures. Therefore, the district’s expenditures, totaling $5,808, in
excess of the approved EEP amount constitute ineligible expenditures.
We notified CDE of the finding via email on June 14, 2021. The CDE
responded by email on June 14, 2021, stating that it would contact the
LEA.
PRC section 26235(f) states:
The Superintendent of Public Instruction shall not distribute funds to an
LEA unless the LEA has submitted to the Energy Commission, and the
Energy Commission has approved, an expenditure plan that outlines the
energy projects to be funded. An LEA shall utilize a simple form
expenditure plan developed by the Energy Commission. The Energy
Commission shall promptly review the plan.…A portion of the funds
may be distributed to an LEA upon request for energy audits and other
plan development activities prior to submission of the plan.
-A37-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The CEC’s 2016 Program Implementation Guidelines (“Energy Planning
Funds Reservation Option,” page 10) state:
LEAs whose first year of eligibility was fiscal year 2013-14, the first
year of the program, had the option of requesting a portion of that year’s
award allocation for energy planning activities in 2013-14 without
submitting an energy expenditure plan(s) to the Energy Commission.
This option was available only for the fiscal year 2013-14 award
allocation and was intended to be used for planning activities for
subsequent fiscal years (2013-14 through 2017-18).
The CEC’s 2016 Program Implementation Guidelines (“Unused Energy
Planning Awards,” page 13) also state that “Any unused energy planning
funds shall be applied toward implementing eligible energy project(s)
approved as part of an LEA’s energy expenditure plan(s).”
Final project completion report submitted late
The district’s final report was submitted on November 25, 2019,
17 months after the reported project completion date of June 30, 2018.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
We recommend that the CDE take appropriate action to recover
Proposition 39 funds that the district expended on project costs that are not
in compliance with the 2016 Program Implementation Guidelines.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit findings via email on February 16,
2021. Keith Bacon, Chief Business Official, responded by letter dated
February 26, 2021. The district’s response letter is included as Attachment
D.
The district’s response to Finding 6 – Final project completion report
submitted late, is as follows:
The district regrets this tardiness of filing. There were various vendor-
related issues that delayed the completion of these documents and as a
result, they were submitted late. It is always the intention of the district
to submit documentation within required deadlines, and this is an
unusual occurrence for these to have been submitted late. In the future,
we will provide a better framework [for] submissions of this type.
-A38-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The district’s response to Finding 3 – Ineligible expenditures, is as
follows:
The district is holding these funds in reserve to be collected by the
California Department of Education (CDE) or to be utilized as instructed,
once we have received guidance. A project of this magnitude is likely to
have a different final expenditure total than planned and this is the result
[of] such an occurrence. In future projects, we will be mindful of the
planning process to ensure complete expenditure of all revenues
collected for projects such as this.
-A39-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
San Francisco Unified School District
Proposition 39 Program
Background The CEC approved San Francisco Unified School District’s EEP for
$1,177,670, consisting of $205,200 for energy management services and
$972,470 for program implementation. The district used its program
implementation funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures* Savings
Interior lighting fixture retrofit; DHW (domestic hot water) heater;
Chin (John Yehall) Elementary $ 427,470 HVAC–chiller/boiler replacement; building envelope–windows/skylights $ 3,525
Interior lighting fixture retrofit; HVAC–chiller/boiler replacement;
El Dorado Elementary 545,000 building envelope–windows/skylights 4,858
Total $ 972,470 $ 8,383
*HVAC: Heating, ventilation, and air conditioning
With these energy efficiency measures, the district reported a combined
SIR of 1.33 and the creation of 5.45 direct job-years.
In addition, the district received $723,104 in planning funds directly from
the CDE, which it used for screening and audits, and program assistance.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Sole-sourced project costs
The district sole-sourced its contract, totaling $32,074, with Strategic
Energy Innovations for several different services, including conservation
management. The district did not provide supporting documentation to
show that it considered other vendors before awarding its contract to
Strategic Energy Innovations. Therefore, we found that the district sole-
sourced this Proposition 39 contract, totaling $32,074.
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h)(1) states, “The Superintendent of Public Instruction
shall require local educational agencies to pay back funds if they are not
used in accordance with state statute or regulations….”
PUC section 388(b) states:
The Department of General Services or any other state or local agency
intending to enter into an energy savings contract or a contract for an
energy retrofit project may establish a pool of qualified energy service
companies based on qualifications, experience, pricing, or other
-A40-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
pertinent factors. Energy service contracts for individual projects
undertaken by any state or local agency may be awarded through a
competitive selection process to individuals or firms identified in the
pool. The pool of qualified energy service companies and contractors
shall be reestablished at least every two years or shall expire.
No projected energy savings identified and/or no signed contract
We reviewed the district’s contracts with Vila Construction, and Zolman
Construction & Development, and determined that the contracts do not
identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Recommendation
We recommend that the CDE take appropriate action to recover
Proposition 39 funds that the district expended on sole-sourced project
costs, in violation of PRC section 26235(c).
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit findings via email on May 20, 2021.
The district did not respond to the audit findings.
-A41-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
San Juan Unified School District
Proposition 39 Program
Background The CEC approved San Juan Unified School District’s EEP Number 1895
for $683,383, consisting of $62,000 for energy management services and
$621,383 for program implementation. In addition, the CEC approved the
district’s EEP Number 1897 for $1,796,672. The district used its program
implementation funds for the following energy efficiency and renewable
energy generation measures:
Proposition 39 Energy Efficiency and Reported
Share Used Renewable Energy Annual Cost
School Site at School Site Generation Measures* Savings
EEP #1895:
Interior/exterior lighting fixture retrofit;
Encina Preparatory High $ 587,510 HVAC–chiller/boiler replacement $ 2 6,755
Transportation Center –
San Juan Unified 3 3,873 Exterior lighting fixture retrofit 2,065
Total, EEP #1895 $ 621,383 $ 2 8,820
EEP #1897:
Interior lighting fixture retrofit;
Bella Vista High $ 1 ,796,672 photovoltaic (solar) $ 122,680
Total, EEP #1897 $ 1 ,796,672 $ 122,680
*HVAC: Heating, ventilation, and air conditioning
With the energy efficiency measures from EEP Number 1895, the district
reported a combined SIR of 1.16 and the creation of 3.48 direct job-years.
With the energy efficiency and renewable energy generation measures
from EEP Number 1897, the district reported a combined SIR of 1.11 and
the creation of 7.55 direct job-years.
In addition, the district received $536,164 in planning funds directly from
the CDE, which it used for screening and audits, program assistance, and
an energy manager.
We audited Proposition 39 program costs to ensure compliance with the
Audit Results
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
No projected energy savings identified and/or no signed contract
The district did not have a signed contract with Innovative Construction
Services for its Proposition 39 planning services. For EEP Number 1895
and EEP Number 1897, we reviewed the district’s contracts with IES and
determined that the contracts do not include the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
-A42-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Final project completion report submitted late
For EEP Number 1895, the district’s final report was submitted on
November 4, 2019, 23 months after the reported project completion date
of December 31, 2017.
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
District’s Response
We informed the district of the audit findings via email on May 6, 2021.
The district did not respond to the audit findings.
-A43-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Sunnyside Union School District
Proposition 39 Program
The CEC approved Sunnyside Union Elementary School District’s EEP
Background
for $218,192, consisting of $21,779 for energy management services,
$4,356 for training, and $192,057 for program implementation. The
district used its program implementation funds for the following energy
efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures Savings
Interior/exterior lighting retrofit; interior linear fluorescent relamping;
Sunnyside Elementary $ 192,057 HVAC Controls–Energy Management System $ 10,056
*HVAC: Heating, ventilation, and air conditioning
With these energy efficiency measures, the district reported a combined
SIR of 1.11 and the creation of 1.08 direct job-years.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
Unspent funds
The district was awarded $272,590 in implementation funds. The district
used only $227,443 of its implementation funds. Therefore, the district has
total unspent funds of $45,147.
On February 22, 2021, we notified CDE of the unspent funds. Prior to
issuance of this report, CDE followed up with the district to recover the
unspent funds.
The CEC’s 2016 Program Implementation Guidelines state on page 5:
The SSPI is responsible for administering awards to LEAs that serve
grades K-12 students. These funds may be used by LEAs for energy
efficiency and clean energy projects, related energy planning, energy
training, energy management, and energy projects with related non-
energy benefits. LEAs are required to submit an energy expenditure plan
to the Energy Commission for consideration and approval. Funds are
released to the LEA only after the Commission approves an LEA’s
energy expenditure plan(s).
PRC section 26240(b) states, “As a condition of receiving funds from
the Job Creation Fund…the entity shall submit a report of its project
expenditures to the Citizens Oversight Board….”
-A44-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Public Resources Code section 26240(h)(1) states, “The Superintendent of
Public Instruction shall require local educational agencies to pay back
funds if they are not used in accordance with state statute or regulations…”
No projected energy savings identified and/or no signed contract
We reviewed the district’s contracts with IES and Trane Energy Solutions,
and determined that the contracts do not identify the projected energy
savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Recommendation
We recommend that the district return the unspent funds to the State.
Although the Proposition 39 program has ended, the unspent funds must
be returned.
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit findings via email on February 22,
2021. Steve Tsuboi, Superintendent-Principal, responded by letter dated
March 2, 2021. The district’s response letter is included as Attachment E.
The district’s response to Finding 2 – Unspent funds, is as follows:
The district agrees with this finding and currently has these funds in an
identified account, pending request for return.
The district’s response to Finding 5 – No projected energy savings
identified and/or no signed contract, is as follows:
The district agrees with the finding, although the Projected Energy
Savings is located in other documents. The district provided such
documents from Trane and an email response from IES and their
justification.
-A45-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Thermalito Union Elementary School District
Proposition 39 Program
Background The CEC approved Thermalito Union Elementary School District’s EEP
for $590,003, which consists of $11,599 for an energy manager and
$578,404 for program implementation. The district used its program
implementation funds for the following energy efficiency measures:
Proposition 39 Reported
Share Used Energy Annual Cost
School Site at School Site Efficiency Measures* Savings
Interior/exterior lighting retrofit; HVAC Controls–
District Office $ 14,277 Programmable/Smart Thermostats $ 924
Interior/exterior lighting retrofit; HVAC Controls–
Heritage Community Day 2 0,648 Programmable/Smart Thermostats 6 46
Maintenance 1 1,510 Interior/exterior lighting retrofit 1,049
Interior/exterior lighting retrofit; HVAC Controls–
Programmable/Smart Thermostats; retrofit interior lamps to
Nelson Avenue Middle 176,814 LED; LED exit signs 8,813
Interior/exterior lighting retrofit; HVAC Controls–
Pioneer Community Day 1 7,163 I nPterorigorra/emxmtearbioler /lSigmhtainrtg T rheetrromfiot;s tHatVsAC Controls– 6 09
Programmable/Smart Thermostats; retrofit interior lamps to
Plumas Avenue Elementary 9 9,569 LED 5,748
Interior/exterior lighting retrofit; HVAC Controls–
Poplar Avenue Elementary 112,442 Programmable/Smart Thermostats; retrofit interior lamps to 6,548
Interior/exterior lighting retrofit; HVAC Controls–
Programmable/Smart Thermostats; HVAC–
Sierra Avenue Elementary 125,981 Packaged/split system AC/heat pump/VRF 5,475
Total $ 578,404 $ 2 9,812
*HVAC: Heating, ventilation, and air conditioning; LED: light-emitting diode; VRF: variable refrigerant flow
With these energy efficiency measures, the district reported a combined
SIR of 1.06 and the creation of 3.24 direct job-years.
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CEC’s
2016 Program Implementation Guidelines and EEP Handbook. We
identified the following audit issues.
No projected energy savings identified and/or no signed contract
We reviewed the district’s contract with IES, and determined that the
contract does not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
Final project completion report submitted late
The district’s final report was submitted on September 25, 2019,
19 months after the reported project completion date of February 28, 2018.
-A46-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PRC section 26240(b) states:
As a condition of receiving funds from the Job Creation Fund…not
sooner than one year but no later than 15 months after an entity
completes its first eligible project with a grant, loan, or other assistance
from the Job Creation Fund…the entity shall submit a report of its
project expenditures to the Citizens Oversight Board….
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
District’s Response
We informed the district of the two audit findings via email on
February 16, 2021. Cody Walker, Assistant Superintendent, responded via
email on February 17, 2021, stating that the district does not have a
response to the findings.
-A47-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Allan Hancock Joint Community College District
Proposition 39 Program
Background The California Community Colleges Chancellor’s Office (CCCCO)
approved Allan Hancock Joint Community College District’s
Proposition 39 Funding Application (Form B) for $1,061,036. The district
used its program implementation funds for the following renewable
energy generation measure:
Proposition 39 Year 1 Savings-to- Direct
Share Used Renewable Energy Cost Investment Job-Years
School Site at School Site Generation Measures* Savings Ratio Created
ALLANH-1617-001
Lompoc Valley Center $ 1 ,061,036 20 kW PV System
Total $ 1,061,036 $ 4 5,509 1.27 4.50
*kW: Killwatt; PV: photovoltaic
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CCCCO’s
Proposition 39 Implementation Guidelines. We identified the following
audit issues.
Sole-sourced project costs
The district sole-sourced its contracts with the following vendors:
JMPE Electrical Engineering Lighting Design (JMPE) − $9,200 for
engineering services;
Ravatt, Albrecht & Associates Inc. − $29,265 for design and bidding
construction;
John R. Byerly Inc. − $23,059 for engineering and inspection;
Tom Little Inspection − $30,515 for DSA inspection services; and
J&P Construction, Inc. − $34,513 for accessible parking lot
resurfacing.
The district did not provide supporting documentation to show that it
considered other vendors before awarding contracts to JMPE, Ravatt,
Albrecht & Associates Inc., John R. Byerly Inc., Tom Little Inspection,
and J&P Construction, Inc. Therefore, we found that the district sole-
sourced these Proposition 39 contracts, totaling $126,552.
In addition, we found that the contract with J&P Construction, Inc.,
totaling $34,513, was for ineligible expenditures (see “Ineligible
expenditures,” on page A50).
The district signed and certified in its application that the funding would
be used for the energy projects identified in its application.
-A48-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h)(2) states, in part, “The Chancellor of the California
Community Colleges shall require a community college to pay back funds
if they are not used in accordance with state statute or regulations…”.
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, in part:
Districts shall not use a sole-source process to award grant proceeds.
Districts may use the best-value criteria as defined in paragraph (1) of
subdivision (c) of Section 20133 of the Public Contract Code to award
funds. Best value is defined as “a value determined by objective criteria
related to price, features, functions, and life-cycle costs.”
Exhibit N (Contracting “Best Practices” Fact Sheet) of the CCCCO’s
Proposition 39 Implementation Guidelines states:
To fully comply with that “Best Value” criteria and the prohibition
against sole source contracting when utilizing [its] Prop 39 funds, a
District will need to engage in a two-step process that accomplishes the
following:
1. Request for Qualification (RFQ): Pre-qualifies energy project
contractors based on several criteria including energy project
history, team member qualifications, firm financial viability, and
experience working with Community Colleges, AND
2. Request for Proposals (RFP): Identifies and evaluates the specific
project workscope, schedule, and other requirements where multiple
contractors (at least two, three would be better) submit proposals for
District evaluation and consideration. Typically, the RFP should
include the following elements and respondent submittal
requirements:
Proposed workscope
Request price and life-cycle economics
Technical proposal and identification of specific equipment to
be installed
Energy savings
Project approach
Schedule
Exceptions
Exhibit N continues:
A comprehensive RFQ/RFP evaluation process should always be used
when implementing Proposition 39 funded projects. This process can
either be combined into a single solicitation, or can use a two-step,
separate RFQ & RFP process.
-A49-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Ineligible expenditures
We reviewed the invoice from Jeff Ploutz Construction, Inc. (dba J&P
Construction), and determined that the district applied Proposition 39
funds to project costs not included in the application approved by the
CCCCO. The district’s contractor for the solar installation project,
Elevated Solar Performance, Inc., did not submit a change order for
asphalt repair or indicate that it was required. In addition, the district
described the scope of work as “ADA Parking Lot Resurfacing” and did
not execute a contract with J&P Construction, Inc., which would have
clarified the scope of work involved. Therefore, we found that $34,513 for
resurfacing the accessible parking lot is ineligible for Proposition 39
funding. As discussed earlier in these audit results, we also found that this
amount was sole-sourced.
The district signed and certified in its application that the funding would
be used for the energy projects identified in its application.
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 10.
Energy Project Implementation,” page 22) states:
Districts will be responsible for the implementation of projects funded
by Proposition 39. If, after approval and during implementation of a
project, the scope changes such that the energy savings, construction
costs, or cost-effectiveness are significantly affected, the Chancellor’s
Office will require that Districts provide a revised Project Application
(Form B) documenting the change of scope.…
Step 10 of the CCCCO’s Proposition 39 Implementation Guidelines also
includes “adding a project not included in the approved Funding
Application” in the list of significant changes.
No projected energy savings identified and/or no signed contract
We reviewed the district’s supporting documentation and found that no
contract was prepared for services provided by J&P Construction.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, “Projects funded by awards shall
require contracts that identify the project specifications, costs, and
projected energy savings.”
Recommendation
We recommend that the CCCCO take appropriate action to recover
Proposition 39 funds that the district expended on sole-sourced project
costs, in violation of PRC section 26235(c).
No additional recommendation is applicable, as the Proposition 39
program has ended.
-A50-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
District’s Response
We informed the district of the three audit findings via email on May 19,
2021. Laura Becker, Director of Business Services, responded via email
on June 1, 2021.
The district’s response to Finding 1 – Sole-sourced project costs, is as
follows:
It is the District’s belief that the contracts in question were appropriately
procured at the time the contracts were signed. During the time of this
project, the District moved to a new financial system and our Purchasing
Supervisor’s computer hard drive [which stored most, if not all, of the
procurement records] crashed.... The Business Services offices have
since moved to storing all documents on a server to prevent this from re-
occurring in the future. In addition, all of the Allan Hancock employees
associated with this project have since retired. The District has
completed an extensive search of email accounts of those employees and
was unable to locate documentation to substantiate that appropriate
procurement provisions were followed.
The district’s response to Finding 3 – Ineligible expenditures, is as
follows:
The District concurs that it did not submit a revised Project Application
(Form B) to the Chancellor’s Office documenting the change in scope
for the additional expense of the ADA Parking Lot Resurfacing.
The district’s response to Finding 5 – No projected energy savings
identified and/or no signed contract, is as follows:
The District has adopted the State of California Uniform Public
Construction Cost Accounting (CUPCCA) informal bidding procedures.
Public Contract Code 22032 states “…(b) Public projects of two hundred
thousand dollars ($200,000) or less may be let to contract by informal
procedures…”. The District followed the CUPCCA procurement process
for the contract in question.
SCO Comment
Our findings and recommendation remains unchanged.
Although the district adopted the CUPCCA informal bidding procedures,
the scope of our audit is to ensure compliance with applicable state statutes
and regulations, which require that all projects shall require contracts that
identify the project specifications, costs, and projected energy savings.
-A51-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Foothill–De Anza Community College District
Proposition 39 Program
Background The CCCCO approved Foothill–De Anza Community College District’s
Proposition 39 Funding Application (Form B) for $2,726,499. The district
used its program implementation funds for the following energy efficiency
measures:
Proposition 39 Year 1 Savings-to- Direct
Share Used Energy Cost Investment Job-Years
School Site at School Site Efficiency Measures* Savings Ratio Created
FOOTHI-1314-005
De Anza College $ 5 45,848 Pool boiler and distribution retrofit
De Anza College 1 33,326 HHW pump VFD retrofit
6 79,174 $ 5 3,215 1.64 4.00
FOOTHI-1415-006
Foothill College 1 95,548 Foothill library boiler replacement and pump upgrade with VFD
1 95,548 5 ,701 1.64 1.11
FOOTHI-1718-001
De Anza College 8 82,239 ATC central chilled water plant cooling towers
8 82,239 7 4,327 1.66 4.94
FOOTHI-1718-002
De Anza College 9 69,538 De Anza exterior LED & stelling garage LED
9 69,538 5 7,974 1.58 5.43
Total $ 2,726,499 $191,217
*HHW: Heating hot water; VFD: variable-frequency drive; ATC: Automatic Temperature Control; LED: light-emitting diode
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CCCCO’s
Proposition 39 Implementation Guidelines. We identified the following
audit issues.
Sole-sourced project costs
The district sole-sourced its contracts with the following vendors:
Gilbane Building Co. − $88,078 for construction and design
management;
Axiom Engineers Inc. − $117,900 for design and professional
services;
HP Inspections Inc. − $5,620 for special inspections and construction;
and
Clean Harbors Environmental Services Inc. − $8,143 for cleaning and
pressure washing cooling towers.
The district did not provide supporting documentation to show that it
considered other vendors before awarding contracts to Gilbane
Building Co., Axiom Engineers Inc., HP Inspections Inc., and Clean
Harbors Environmental Services Inc.. Therefore, the district sole-sourced
these Proposition 39 contracts, totaling $219,741.
-A52-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
PRC section 26235(c) states, in part, “A community college district or
LEA shall not use a sole source process to award funds pursuant to this
chapter.”
PRC section 26240(h)(2) states, in part, “The Chancellor of the California
Community Colleges shall require a community college to pay back funds
if they are not used in accordance with state statute or regulations…”.
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, in part:
Districts shall not use a sole-source process to award grant proceeds.
Districts may use the best-value criteria as defined in paragraph (1) of
subdivision (c) of Section 20133 of the Public Contract Code to award
funds. Best value is defined as “a value determined by objective criteria
related to price, features, functions, and life-cycle costs.”
Exhibit N (Contracting “Best Practices” Fact Sheet) of the CCCCO’s
Proposition 39 Implementation Guidelines states:
To fully comply with that “Best Value” criteria and the prohibition
against sole source contracting when utilizing [its] Prop 39 funds, a
District will need to engage in a two-step process that accomplishes the
following:
1. Request for Qualification (RFQ): Pre-qualifies energy project
contractors based on several criteria including energy project
history, team member qualifications, firm financial viability, and
experience working with Community Colleges, AND
2. Request for Proposals (RFP): Identifies and evaluates the specific
project workscope, schedule, and other requirements where multiple
contractors (at least two, three would be better) submit proposals for
District evaluation and consideration. Typically, the RFP should
include the following elements and respondent submittal
requirements:
Proposed workscope
Request price and life-cycle economics
Technical proposal and identification of specific equipment to
be installed
Energy savings
Project approach
Schedule
Exceptions
Exhibit N continues:
A comprehensive RFQ/RFP evaluation process should always be used
when implementing Proposition 39 funded projects. This process can
either be combined into a single solicitation, or can use a two-step,
separate RFQ & RFP process.
-A53-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
No projected energy savings identified and/or no signed contract
We reviewed the district’s contracts with Environmental Systems Inc.,
Kitchell CEM Inc., Comfort Dynamics Inc., and Clear Blue Energy Corp.,
and determined that the contracts do not identify the projected energy
savings. In addition, no contract was prepared for services provided by
American Reprographics Co.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, “Projects funded by awards shall
require contracts that identify the project specifications, costs, and
projected energy savings.”
Recommendation
We recommend that the CCCCO take appropriate action to recover
Proposition 39 funds that the district expended on sole-sourced project
costs, in violation of PRC section 26235(c).
No additional recommendation is applicable, as the Proposition 39
program has ended.
District’s Response
We informed the district of the audit finding via email on May 19, 2021.
Susan Cheu, Vice-Chancellor, Business Services, responded by letter
dated June 1, 2021. The district’s response letter is included as
Attachment F.
The district’s response to Finding 1 – Sole-sourced project costs, is as
follows:
Gilbane Building Co. – This contract leveraged the competitive bid
award RFP No. 1073 to Gilbane for Construction Management / Program
Management awarded in 2007 as part of District Measure C.
This contract was separate from, but related to an existing Measure C
project contract with Gilbane for the provision of long-term
construction/project management services. As such, Gilbane is an
integral part of District’s construction/program management services,
and thus uniquely qualified.
In addition, the Public Contract Code § 20652 allows us to leverage other
agencies competitive bid contracts, in this case we leveraged our own
competitive bid contract. By leveraging the competitive bid procurement
process and existing relationship with Gilbane, they were able to begin
work immediately and expedite the project.
Axiom Engineers – The original agreement ($99,800) was submitted to
the governing board and approved on 04/02/2018. This contract was
awarded based on Government Code §53060 Special/Professional
Services. Note the Board Agenda item states “… during the contracting
phase, Axiom will assist in the bid process.” A subsequent change order
in the amount of $18,100 was approved by the governing board on
02/04/2019.
-A54-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
HP Inspectors – This contract did not exceed the District’s small
purchase threshold (per Purchasing Policy BP 3140, contracts greater
than $10,000 require competitive bid process) which is stricter than
Federal small purchase threshold of $100,000.
In addition, special/professional services are not required to go out to bid
per Government Code 4525.
Clean Harbors – this contract leveraged the competitive bid award RFP
No. 1739 [Hazardous Materials] Waste Collection Services approved by
the governing board on 12/07/2015.
This contract was separate but related to the hazardous material services
provided by Clean Harbors in the RFP, and awarded through the
[California Uniform Public Construction Cost Accounting Act] process.
In addition, this separate contract did not exceed the District’s small
purchase threshold (per Purchasing Policy BP 3140, contracts greater
than $10,000 require competitive bid process) which is stricter than [the]
Federal small purchase threshold of $100,000.
The district’s response to Finding 5 – No projected energy savings
identified and/or no signed contract, is as follows:
The district was under the impression that the project review by NAM
[Newcomb Anderson McCormick] would suffice to meet the
requirement for statement of energy savings. It acknowledges that it did
not include this information in the noted contracts….
[Regarding] American Reprographics Co., due to the low dollar amount,
this [contract] was not required to go to bid.
SCO Comment
Our findings and recommendation remain unchanged.
The scope of our audit was to ensure compliance with state statutes and
regulations. The district cites reliance on Government Code section 53060,
Public Contract Code section 20652, and its own procurement policies to
support its use of sole-sourced contracts. However, PRC section 26235(c)
states:
A community college district or LEA shall not use a sole source process
to award funds pursuant to this chapter. A community college or LEA
may use the best value criteria as defined in paragraph (1) of
subdivision (c) of Section 20133 of the Public Contract Code to award
funds pursuant to this chapter [emphasis added].
Furthermore, the CCCCO’s Proposition 39 Implementation Guidelines
(“Step 9. Fully Develop Project Workscope, Schedule and Contracts for
Project Implementation,” page 21) states, in part,
These Guidelines defer to the District’s own procurement regulations
and procedures as long as they reflect applicable state and local laws
and regulations and are not in conflict with the minimum standards
specified below:
Projects funded by awards shall require contracts that identify the
project specifications, costs, and projected energy savings.
-A55-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Districts shall follow applicable law related to contractor
qualifications, licensing, and certification requirements related to
the project.
Districts shall not use a sole‐source process to award grant proceeds.
Districts may use the best value criteria as defined in paragraph (1)
of subdivision (c) of Section 20133 of the Public Contract Code to
award funds. Best value is defined as “a value determined by
objective criteria related to price, features, functions, and life‐cycle
costs” [emphasis added].
As noted in the body of the finding, Exhibit N of the CCCCO’s
Proposition 39 Implementation Guidelines provides additional guidance
for college districts on how to best comply with the Proposition 39
Program prohibition against sole-source bids.
Concerning the district’s contract with Gilbane Building Co., the bidding
process cited in the district’s response took place in 2006. The initial
contract with Gilbane Building Co., which resulted from that bidding
process, was in effect from July 1, 2008, through June 30, 2009. The
Proposition 39 contract with Gilbane Building Co. was in effect from
January 1, 2019, through December 31, 2019. Because the RFQ process
was conducted 13 years prior to the Proposition 39 project and involved
the issuance of two separate contracts for widely different time periods,
we concluded that the district relied on its previous experience with this
vendor rather than conducting a new bidding process. A competitive
bidding process would have allowed other vendors to compete for the
related energy work at the district.
Therefore, although the district followed other provisions contained in
state statutes related to contracting, and its own procurement regulations
and procedures, we found that it did not follow the requirements of PRC
section 26235(c) for its contracts with Gilbane Building Co., Axiom
Engineers Inc., HP Inspections Inc., and Clean Harbors Environmental
Services Inc.
-A56-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Glendale Community College District
Proposition 39 Program
Background The CCCCO approved Glendale Community College District’s
Proposition 39 Funding Application (Form B) for $1,913,134. The district
used its program implementation funds for the following energy efficiency
measures:
Proposition 39 Year 1 Savings-to- Direct
Share Used Energy Cost Investment Job-Years
School Site at School Site Efficiency Measures* Savings Ratio Created
GLENDA-1415-001
Advanced Tech HVAC Controls–Economizer –
Glendale Community College $ 8 0,165 Electric Savings
Advanced Tech HVAC Controls–Economizer –
Glendale Community College 1 16,082 Gas Savings
Library HVAC Controls–Economizer –
Glendale Community College 1 16,082 Electric Savings
Glendale Community College 1 16,082 Library HVAC Controls–Economizer – Gas Savings
4 28,411 $ 4 1,983 1.39 3.52
GLENDA-1718-001
Glendale Community College 5 99,402 Stadium Lighting Retrofit
5 99,402 $ 1 4,355 1.39 3.46
GLENDA-1718-002
Glendale Community College 1 95,232 Verdugo Gym BAS Upgrade
1 95,232 $ 1 9,389 1.39 2.00
GLENDA-1718-003
Glendale Community College 6 90,089 San Gabriel BAS Upgrade
6 90,089 $ 5 1,325 1.39 6.62
Total $ 1,913,134 $ 127,052
*HVAC: Heating, ventilation, and air conditioning; BAS: building automation system
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CCCCO’s
Proposition 39 Implementation Guidelines. We identified the following
audit issue.
No projected energy savings identified and/or no signed contract
We reviewed the district’s contracts with Rosendin Electric for the
Stadium Lighting project, Sunbelt Controls for the Verdugo Gym – BAS
project, and Emcor Services (Mesa Energy Systems, Inc.) for the San
Gabriel – BAS project, and determined that the contracts do not identify
the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
-A57-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, “Projects funded by awards shall
require contracts that identify the project specifications, costs, and
projected energy savings.”
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
District’s Response
We informed the district of the audit findings via email on May 20, 2021.
Susan Courtey, Director of Business Services, responded by letter dated
June 1, 2021. The district’s response letter is included as Attachment G.
The district’s response to the audit finding is as follows:
The projected and expected energy savings for the District’s energy
conservation measures were included in the Energy Efficiency Measure
(EEM) Matrix as part of Board Resolution No. 24-2018-2019 approved
at the June 18, 2019 board meeting. The Prop 39 EEMs (1-4) were noted
as such in the matrix submitted in support of the energy conservation
measures.
The scopes of work and the specifications that were required to be
implemented by qualified contractors to generate the savings were
included in the RFPs issued for each respective project. Due to the
complexity of the systems and the fact that all components of the systems
need to work together to achieve the optimum savings, each RFP listed
very detailed scopes of work and specifications along with the
expectations for the contractor’s installation and the required
performance of those systems. The contractor requirements also included
the commissioning and an extended guarantee for the systems.
The energy savings numbers were not expressly included in the RFPs
partially because it would have created confusion around whether or not
a contractual savings guarantee was required by respective bidders rather
than the system as a whole and more importantly would have limited the
contractor’s that would have been able to respond. The college was
looking for contractors with the most cost effective skilled trade labor to
implement the systems as a whole. Traditional mechanical, electrical,
and controls contractors don’t necessarily have in-house energy
engineers and might have considered themselves disqualified by an RFP
with implied energy savings guarantees. In order to make sure the most
qualified contractors responded to the RFPs and at the lowest cost, the
energy savings and project budgets included in Board Resolution
No. 24-2018-2019 were generated by the District, prior to the projects
and associated RFPs being approved by the Board.
The systems covered under the agreement are complex and are a
combination of following components:
The projected energy savings approved by the Board Resolution
The comprehensive specifications of the RFP
The obligations under the individual contracts
The required performance of the system
-A58-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Based upon the foregoing, it is the District’s position that these
components taken as whole would equate to contracts that identify
project specification, costs, and projected energy savings that would fall
within the intent of PRC Section 26206(d).
SCO Comment
Our finding remains unchanged.
Although we recognize that the district participated in the program to the
best of its ability, the scope of our audit is to ensure compliance with state
statute and regulations, which require that the projected energy savings be
identified in the awarded contract.
-A59-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
San Francisco Community College District
Proposition 39 Program
Background The CCCCO approved San Francisco Community College District’s
Proposition 39 Funding Application (Form B) for $2,483,902. The district
used its program implementation funds for the following energy efficiency
measures:
Proposition 39 Year 1 Savings-to- Direct
Share Used Energy Cost Investment Job-Years
School Site at School Site Efficiency Measures* Savings Ratio Created
SANFRA-1516-001
San Francisco Downtown CC Center $ 602,567 Downtown Center–Boiler Replacement
San Francisco Downtown CC Center 456,138 Downtown Center–VFD add-on to CHW and HHW Pumps
San Francisco Downtown CC Center 363,795 Downtown Center–Replace chiller
San Francisco Downtown CC Center 132,778 Downtown Center–Replace cooling tower
San Francisco Downtown CC Center 439,940 Downtown Center–Controls upgrade
San Francisco Downtown CC Center 358,078 Downtown Center–AHU motor VFDs and controls
San Francisco Downtown CC Center 130,606 Downtown Center–AHU motor replacement
Total $ 2,483,902 $ 188,644 1.18 19.75
*VFD: Variable-frequency drive; CHW: chilled water; HHW: heating hot water; AHU: air handling unit
Audit Results We audited Proposition 39 program costs to ensure compliance with the
Job Creation Fund program guidelines, as well as the CCCCO’s
Proposition 39 Implementation Guidelines. We identified the following
audit issue:
No projected energy savings identified and/or no signed contract
We reviewed the district’s contract with Southland Industries, and
determined that the contract does not identify the projected energy savings.
PRC section 26206(d) states, “All projects shall require contracts that
identify the project specifications, costs, and projected energy savings.”
The CCCCO’s Proposition 39 Implementation Guidelines (“Step 9. Fully
Develop Project Workscope, Schedule and Contracts for Project
Implementation,” page 21) states, “Projects funded by awards shall
require contracts that identify the project specifications, costs, and
projected energy savings.”
Recommendation
No recommendation is applicable, as the Proposition 39 program has
ended.
District’s Response
We informed the district of the audit finding via email on March 15, 2021.
Marian Lam, Assistant Director of Capital Planning, responded via email
on March 25, 2021.
-A60-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
The district’s response to the finding is as follows:
The district’s contract with Southland Industries comprises scope of
work and basis of design of projected energy savings as identified
by Enpowered Solutions (formerly Enernoc and Cogent Energy) and
energy calculations provided by Newcomb Anderson McCormick
(NAM).
1. Enpowered Solutions prepared a report for the District with energy
savings measures for Prop. 39 along with project scope. The
Downtown Center was one of those identified projects.
2. NAM (now Wildan Energy) assisted the District with completing all
required Prop. 39 paperwork for submission to the State. NAM
provided the energy calculations based on the design and submitted
it and received approval for the Prop. 39 funding.
3. The design team from S&K Engineers provided engineering for the
scope of the project as outlined by Enpowered, and developed plans
and specifications for bidding based on the projected energy savings
calculations from NAM that [were] approved by the State for
Prop. 39 funding.
4. The district awarded the contract to Southland Industries. On Page 2
of 4 of the Agreement Form it is stipulated that:
The parties hereto incorporate by reference herein the Contract
Documents, which include:
1. The Drawings and Specifications,
2. The General Conditions and any Supplemental or Special
Conditions,
3. The Bid Documents (as Defined in the Instructions to Bidders),
and
4. Any documents incorporated by reference into the foregoing
documents.
The Energy Conservation Audit Report developed by Enpowered
Solutions and the energy calculations provided by NAM are not
specifically named in the contract documents but were reference
documents shared with the engineer as the basis of design to create the
project scope, generate drawings and specifications, and were integral in
all aspects of this project. These reference documents were also shared
with the contractor, Southland Industries, that constructed and executed
the plans.
SCO Comment
Our finding remains unchanged.
We agree that the district identifies the projected energy savings in the
Energy Conservation Audit Report prepared by Enpowered Solutions, and
in the calculations provided by NAM. However, these two documents
were not referenced as part of the district’s contract documents. The scope
of our audit is to ensure compliance with state statutes and regulations,
which require that the projected energy savings be identified in the
awarded contract.
-A61-
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment A—
Antelope Valley Union High School District’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment B—
Children of Promise Preparatory Academy’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment C—
Madera Unified School District’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment D—
Romoland School District’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment E—
Sunnyside Union School District’s Response
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment F—
Foothill De Anza Community College District’s Response
–
to Audit Results
Program Audit of the California Clean Energy Jobs Act Proposition 39 Program
Attachment G—
Glendale Community College District’s Response
to Audit Results
State Controller’s Office
Division of Audits
Post Office Box 942850
Sacramento, CA 94250
http://www.sco.ca.gov
S21-39M-0001